947 S ST ANDREWS PL 90019
Certificate Information: 947 S ST ANDREWS PL 90019
- Application / Permit
- 22016-10000-39206
- Plan Check / Job No.
- B22LA26545
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story Seismic retrofit per LABC Chapter 93: Install one (1) two ways Special Steel Cantilever Column
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/14/2024
Permit Application Status History
| Submitted | 1/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | BIDYUT RATH |
| Corrections Issued | 1/31/2023 | BIDYUT RATH |
| Quality Review Completed | 2/7/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/30/2023 | BIDYUT RATH |
| Applicant returned to address corrections | 4/20/2023 | JESSE VIDUYA |
| Plan Check Approved | 5/1/2023 | BIDYUT RATH |
| Issued | 5/24/2023 | APPLICANT |
| OK for CofC | 6/14/2024 | DARRYL ARNOLD |
| CofC Issued | 6/14/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/19/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Twenty One Retrofit Inc; Lic. No.: 1065687-B | 17700 S AVALON BLVD UNIT #345 CARSON, CA 90746 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2024 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 4/17/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 4/17/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 4/19/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 4/24/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 4/26/2024 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 4/26/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/26/2024 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 4/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/7/2024 | Approved | DARRYL ARNOLD |
| Final | 5/17/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/17/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/13/2024 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 6/13/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/14/2024 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 6/14/2024 | Approved | DARRYL ARNOLD |