300 1/2 N ENTRADA DR 90402
Certificate Information: 300 1/2 N ENTRADA DR 90402
- Application / Permit
- 22016-10000-39172
- Plan Check / Job No.
- B22LA26502
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU WITH 2-STORY ADDITION PER LAMC 12.22 A.33 (c)-(d) ***COMPLY WITH DEPARTMENT ORDER*** ***FIRE SPRINKLER 13D REQUIRED***
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | DANIEL SANJUAN |
| Corrections Issued | 12/29/2022 | DANIEL SANJUAN |
| Plan Check Approved | 5/7/2024 | KHUONG TRUONG |
| Issued | 5/7/2024 | APPLICANT |
| Permit Finaled | 4/7/2025 | CLAUDIO MORENO |
| CofO Issued | 4/7/2025 | CLAUDIO MORENO |
| Permit Finaled | 4/7/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/14/2023 | RIDWAN HARDY |
| Coastal Zone | Cleared | 4/4/2024 | JASON CHAN |
| Coastal Zone | Cleared | 4/4/2024 | JASON CHAN |
| Coastal Zone | Cleared | 4/4/2024 | JASON CHAN |
Contact Information
| Contractor | Fresh N Easy Builders & Hvac Inc; Lic. No.: 1094004-B | 10346 COMMERCE AVE #1 TUJUNGA, CA 91042 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2024 | Partial Approval | JOHN MATTILLO |
| Pre-Inspection | 6/28/2024 | Approved | JOHN MATTILLO |
| Footing/Foundation/Slab | 9/19/2024 | Partial Approval | RYAN BARNES |
| PLUMBING-Rough | 9/19/2024 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 11/18/2024 | Partial Approval | RYAN BARNES |
| FLOOD-Proofing Certificate | 11/18/2024 | Not Ready for Inspection | RYAN BARNES |
| Green Building Rough | 11/18/2024 | Approved | RYAN BARNES |
| Verify Sprinkler Sign Off | 11/18/2024 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 12/10/2024 | Conditional Approval | RYAN BARNES |
| ELECTRICAL-Rough | 12/10/2024 | Approved | RYAN BARNES |
| FLOOD-Proofing Certificate | 12/10/2024 | Not Ready for Inspection | RYAN BARNES |
| HVAC-Rough | 12/10/2024 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 12/10/2024 | Approved | RYAN BARNES |
| PLUMBING-Rough | 12/10/2024 | Approved | RYAN BARNES |
| Rough-Elec/Plmb/HVAC | 12/10/2024 | Approved | RYAN BARNES |
| Verify Sprinkler Sign Off | 12/10/2024 | Approved | RYAN BARNES |
| Wood Frame | 12/10/2024 | Approved | RYAN BARNES |
| Insulation | 12/20/2024 | Approved | RYAN BARNES |
| Drywall Nailing | 1/3/2025 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 1/3/2025 | Approved | RYAN BARNES |
| Shower Pan | 1/3/2025 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | RYAN BARNES |
| FLOOD-Proofing Certificate | 3/28/2025 | Approved | RYAN BARNES |
| Final | 3/28/2025 | Conditional Approval | RYAN BARNES |
| Footing/Foundation/Slab | 3/28/2025 | Approved | RYAN BARNES |
| Green Building Final | 3/28/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 3/28/2025 | Approved | RYAN BARNES |