147 3/4 E 89TH ST 90003

Certificate Information: 147 3/4 E 89TH ST 90003

Application / Permit
22016-10000-39116
Plan Check / Job No.
B22LA26460
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISITING 1-STORY RECREATION ROOM TO ACCESSORY DWELLING UNIT PER STATE LAW
Permit Issued
Issued on 4/30/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 12/28/2022 MINA HABILI
Corrections Issued 12/28/2022 MINA HABILI
Applicant returned to address corrections 4/29/2024 MINA HABILI
Plan Check Approved 4/30/2024 GEORGE ALVAREZ
Issued 4/30/2024 APPLICANT
CofO in Progress 10/3/2025 MICHAEL LEWIS
No Progress 10/7/2025 DEROLD HAUFF
CofO in Progress 10/7/2025 DEROLD HAUFF
CofO in Progress 10/7/2025 SABAS ALONSO
Permit Finaled 10/8/2025 DEROLD HAUFF
CofO Issued 10/8/2025 DEROLD HAUFF
Permit Finaled 10/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/19/2023 JEANIE LAM
Sewer availability Cleared 1/19/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/30/2023 JEANIE LAM
Construction near power lines Cleared 4/28/2023 RIDWAN HARDY
Tenant Habitability Plan Cleared 4/29/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 2/18/2025 Not Ready for Inspection ANTHONY RAMOS
Shower Pan 2/18/2025 Not Ready for Inspection ANTHONY RAMOS
ELECTRICAL-Rough 2/25/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 2/25/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 2/25/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 3/21/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/21/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 4/17/2025 Approved ANTHONY RAMOS
Shower Pan 4/17/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 5/21/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Final 8/4/2025 No Access for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 8/11/2025 Partial Approval JOHN QUINTANILLA
ELECTRICAL-Final 8/18/2025 Approved JOHN QUINTANILLA
HVAC-Final 8/22/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 8/22/2025 Approved BARRY HACHE
Verify Rec and Parks Fee Memo 8/22/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 10/3/2025 Approved MICHAEL LEWIS
Final 10/3/2025 OK to Issue CofO MICHAEL LEWIS
HVAC-Final 10/3/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 10/3/2025 Approved MICHAEL LEWIS
Final 10/6/2025 OK to Issue CofO SABAS ALONSO