1545 1/2 W 56TH ST 90062

Certificate Information: 1545 1/2 W 56TH ST 90062

Application / Permit
22016-10000-39083
Plan Check / Job No.
B22LA26416
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
A CONVERSION OF AN EXISITING 4-CAR GARAGE INTO A NEW DETACHED ACCESSORY DWELLING UNIT (673 SQFT) PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) NO SQFT ADDED, ALL WORK DONE PER WFPP
Permit Issued
Issued on 4/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 1/3/2023 KHUONG TRUONG
Corrections Issued 1/5/2023 KHUONG TRUONG
Building Plans Picked Up 1/9/2023 APPLICANT
Plan Check Approved 4/3/2023 DANIEL SMILEY
Issued 4/6/2023 APPLICANT
CofO in Progress 3/8/2024 SABAS ALONSO
Permit Finaled 3/12/2024 DEROLD HAUFF
CofO Issued 3/12/2024 DEROLD HAUFF
Permit Finaled 3/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 3/29/2023 RAFAEL FONTES
Address approval Cleared 3/30/2023 TREVOR QUAN
Sewer availability Cleared 3/30/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/31/2023 TREVOR QUAN

Contact Information

Contractor E A C Construction Inc; Lic. No.: 851569-B 3923 3RD AVE      LOS ANGELES, CA 90008

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/20/2023 Conditional Approval SABAS ALONSO
Deputy Other (see comments) 6/20/2023 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 6/20/2023 Approved SCOTT FINNILA
Sewer 6/20/2023 Approved SCOTT FINNILA
Underground Mechanical 6/20/2023 Partial Approval SCOTT FINNILA
Deputy Drilled-In Anchors 6/22/2023 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/12/2023 Approved SABAS ALONSO
Green Building Rough 7/12/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 7/12/2023 Approved SABAS ALONSO
Sewer 7/12/2023 Approved SABAS ALONSO
Underground Mechanical 7/12/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 8/3/2023 Approved SABAS ALONSO
Green Building Rough 8/3/2023 Approved SABAS ALONSO
HVAC-Rough 8/3/2023 Corrections Issued SABAS ALONSO
Shower Pan 8/3/2023 Corrections Issued SABAS ALONSO
Insulation 8/9/2023 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 8/9/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 8/18/2023 Approved STUART CHAPMAN
Drywall Nailing 8/29/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 8/29/2023 Approved SABAS ALONSO
Shower Pan 8/29/2023 Approved SABAS ALONSO
Final 11/21/2023 Corrections Issued SABAS ALONSO
Green Building Final 11/21/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved SABAS ALONSO
Service/Power Release 11/21/2023 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 11/21/2023 Approved SABAS ALONSO
Final 12/6/2023 Corrections Issued SABAS ALONSO
Final 3/6/2024 OK to Issue CofO SABAS ALONSO