1545 1/2 W 56TH ST 90062
Certificate Information: 1545 1/2 W 56TH ST 90062
- Application / Permit
- 22016-10000-39083
- Plan Check / Job No.
- B22LA26416
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- A CONVERSION OF AN EXISITING 4-CAR GARAGE INTO A NEW DETACHED ACCESSORY DWELLING UNIT (673 SQFT) PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) NO SQFT ADDED, ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 4/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | KHUONG TRUONG |
| Corrections Issued | 1/5/2023 | KHUONG TRUONG |
| Building Plans Picked Up | 1/9/2023 | APPLICANT |
| Plan Check Approved | 4/3/2023 | DANIEL SMILEY |
| Issued | 4/6/2023 | APPLICANT |
| CofO in Progress | 3/8/2024 | SABAS ALONSO |
| Permit Finaled | 3/12/2024 | DEROLD HAUFF |
| CofO Issued | 3/12/2024 | DEROLD HAUFF |
| Permit Finaled | 3/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 3/29/2023 | RAFAEL FONTES |
| Address approval | Cleared | 3/30/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 3/30/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2023 | TREVOR QUAN |
Contact Information
| Contractor | E A C Construction Inc; Lic. No.: 851569-B | 3923 3RD AVE LOS ANGELES, CA 90008 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2023 | Conditional Approval | SABAS ALONSO |
| Deputy Other (see comments) | 6/20/2023 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 6/20/2023 | Approved | SCOTT FINNILA |
| Sewer | 6/20/2023 | Approved | SCOTT FINNILA |
| Underground Mechanical | 6/20/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 6/22/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/12/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 7/12/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 7/12/2023 | Approved | SABAS ALONSO |
| Sewer | 7/12/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/12/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 8/3/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/3/2023 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 8/3/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 8/9/2023 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/29/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/29/2023 | Approved | SABAS ALONSO |
| Shower Pan | 8/29/2023 | Approved | SABAS ALONSO |
| Final | 11/21/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/21/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 11/21/2023 | Approved | SABAS ALONSO |
| Final | 12/6/2023 | Corrections Issued | SABAS ALONSO |
| Final | 3/6/2024 | OK to Issue CofO | SABAS ALONSO |