1630-1632 W 209TH ST 90501
Certificate Information: 1630-1632 W 209TH ST 90501
- Application / Permit
- 22016-10000-39082
- Plan Check / Job No.
- B22LA26409
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- convert existing attached garage to ADU in existing one story single family dwelling per CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | AUNG SOE |
| Corrections Issued | 1/9/2023 | AUNG SOE |
| Building Plans Picked Up | 1/17/2023 | APPLICANT |
| Applicant returned to address corrections | 2/27/2023 | FERNANDO FLORES |
| Plan Check Approved | 2/28/2023 | DANIEL SANJUAN |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 12/12/2023 | JAMES CHAVEZ |
| Permit Finaled | 12/14/2023 | DONALD CRICHLOW |
| CofO Issued | 12/14/2023 | DONALD CRICHLOW |
| Permit Finaled | 12/14/2023 | DONALD CRICHLOW |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2023 | CINDY QI |
| Sewer availability | Cleared | 2/22/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | CINDY QI |
| Tenant Habitability Plan | Cleared | 2/27/2023 | MICHAEL SOTO |
| ZI | Cleared | 2/27/2023 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/24/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 3/24/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/30/2023 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/14/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/14/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 4/28/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/26/2023 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/25/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/25/2023 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 7/25/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/13/2023 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 10/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 10/13/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/13/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 10/13/2023 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 10/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/31/2023 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/31/2023 | Approved | EUGENE CASSIDY |
| Final | 11/15/2023 | OK to Issue CofO | JAMES CHAVEZ |