612 S BROADWAY 8th floor 90014
Certificate Information: 612 S BROADWAY 8th floor 90014
- Application / Permit
- 22016-10000-39071
- Plan Check / Job No.
- B22LA26398
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- INSTALLATION OF NEW OUTDOOR BAR AND BACK ROOM SUPPORT FOR (E) RESTAURANT. SEE COMMENTS
- Permit Issued
- Issued on 3/28/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/28/2025
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 2/10/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/14/2023 | RODOLFO ARIAS |
| Building Plans Picked Up | 2/16/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 4/25/2023 | APPLICANT |
| Applicant returned to address corrections | 6/28/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/27/2024 | SERGIO GUTIERREZ |
| Issued | 3/28/2024 | APPLICANT |
| Permit Finaled | 3/12/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | AMAAN MALIK |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 2/24/2023 | AMAAN MALIK |
| ZA Case | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 2/24/2023 | RUBEN VASQUEZ |
| HPOZ | Cleared | 4/27/2023 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 4/27/2023 | LAMBERT GIESSINGER |
| Miscellaneous | Cleared | 4/27/2023 | LAMBERT GIESSINGER |
| Food Service Establishment | Cleared | 11/20/2023 | KENNETH BROWNE |
| Fire Marshal Fire Life Safety | Cleared | 2/7/2024 | FIRE DEPARTMENT |
| "D" conditions | Cleared | 2/13/2024 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 2/13/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/13/2024 | RUBEN VASQUEZ |
| Supp. Use District POD/CDO/TDO | Cleared | 2/13/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 2/13/2024 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 2/16/2024 | EDDIE GARIN |
| Food establishment approval | Cleared | 2/27/2024 | LACDHS APPROVED |
| Redevelopment Project Area | Cleared | 2/28/2024 | ELIZABETH GALLARDO |
Contact Information
| Contractor | Analog Construction; Lic. No.: 1058496-B | 1910 W SUNSET BLVD 430 LOS ANGELES, CA 90026 |
| Engineer | Youngblood,, Charles St Denny; Lic. No.: C45031 | 556 SEGOVIA AVE SAN GABRIEL, CA 91775 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 1/3/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 1/3/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |
| T-Bar Ceiling | 1/23/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |
| T-Bar Ceiling | 1/28/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 1/29/2025 | Partial Approval | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Not Ready | PAUL BAZERKANIAN |
| Final | 3/12/2025 | Permit Finaled | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 3/12/2025 | Approved | PAUL BAZERKANIAN |