1920 S CYRIL AVE 90032
Certificate Information: 1920 S CYRIL AVE 90032
- Application / Permit
- 22016-10000-39016
- Plan Check / Job No.
- B22LA22765
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | DANIEL YIP |
| Corrections Issued | 12/26/2022 | DANIEL YIP |
| Quality Review Completed | 12/27/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/17/2023 | DANIEL YIP |
| Plan Check Approved | 7/25/2023 | DANIEL YIP |
| No Progress | 8/30/2023 | DANIEL YIP |
| Plan Check Approved | 8/30/2023 | DANIEL YIP |
| No Progress | 9/7/2023 | DANIEL YIP |
| Plan Check Approved | 9/7/2023 | DANIEL YIP |
| Issued | 10/3/2023 | APPLICANT |
| CofO in Progress | 3/13/2024 | LILIANA PORTILLO |
| CofO Issued | 3/19/2024 | DEROLD HAUFF |
| Permit Finaled | 3/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/25/2023 | KIRK LINKLATER |
| Address approval | Cleared | 2/1/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 2/1/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 2/1/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2023 | AMAAN MALIK |
| Construction near power lines | Cleared | 5/5/2023 | TINA MIRANDA |
Contact Information
| Contractor | Chi Cheng Construction Corp; Lic. No.: 1075660-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/2/2023 | Partial Approval | AMY COLIN |
| Gas Test | 11/2/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 11/2/2023 | Partial Approval | AMY COLIN |
| Underground Mechanical | 11/2/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 11/7/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/30/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 12/8/2023 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 12/8/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 12/8/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/12/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 12/12/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Approved | AMY COLIN |
| HVAC-Rough | 12/12/2023 | Approved | AMY COLIN |
| Insulation | 12/15/2023 | Not Ready for Inspection | AMY COLIN |
| Insulation | 12/19/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/19/2023 | Approved | AMY COLIN |
| Drywall Nailing | 12/27/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/27/2023 | Approved | AMY COLIN |
| Shower Pan | 12/27/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 2/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/2/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/2/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/2/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/8/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/12/2024 | OK to Issue CofO | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/12/2024 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 3/12/2024 | Not Required | LILIANA PORTILLO |