1851 N LOBDELL PL 90026
Certificate Information: 1851 N LOBDELL PL 90026
- Application / Permit
- 22016-10000-38997
- Plan Check / Job No.
- B22LA26327
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERET TWO STORY STORAGE ROOM/REC ROOM TO ADU WITH NEW BALCONY
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Current Status
- Issued on 5/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | JAD BASMA |
| Corrections Issued | 2/23/2023 | JAD BASMA |
| Quality Review Completed | 3/2/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/5/2023 | JAD BASMA |
| Issued | 5/9/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2023 | CELINA MORENO |
| Sewer availability | Cleared | 3/15/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/15/2026 |
Inspection Request History
| BUILDING-Rough-Frame | 5/12/2023 | Partial Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 5/12/2023 | Partial Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/12/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 5/12/2023 | Partial Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 10/9/2024 | Corrections Issued | THOMAS LOGRASSO |
| Wood Frame | 10/9/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/28/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 10/28/2024 | Approved | ROY SPAULDING |
| Wood Frame | 10/28/2024 | Partial Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/1/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/1/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 1/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/24/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/11/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/27/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 1/27/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/6/2026 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/6/2026 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/18/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/18/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/18/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/18/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/23/2026 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/23/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/2/2026 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/2/2026 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/2/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 5/5/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/5/2026 | Approved | HAMIK HARTOUNIAN |