625 N MICHELTORENA ST 90026
Certificate Information: 625 N MICHELTORENA ST 90026
- Application / Permit
- 22016-10000-38951
- Plan Check / Job No.
- B22LA26258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan ** Addition to and conversion of (E) Detached Garage at rear of the lot to an Accessory Dweeling Unit (ADU) per CA Govt. Code 65852.2(e)(1)(A) using the Wood Frame Prescriptive Provisions
- Permit Issued
- Issued on 7/17/2023
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2022 | EDWIN ESPIN |
| Corrections Issued | 1/3/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 2/8/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 3/23/2023 | EDWIN ESPIN |
| Plan Check Approved | 7/15/2023 | EDWIN ESPIN |
| Issued | 7/17/2023 | APPLICANT |
| CofO in Progress | 3/12/2025 | FREDDIE RIVERA |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
| CofO Issued | 3/13/2025 | DEROLD HAUFF |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2023 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 1/9/2023 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/12/2023 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 3/2/2023 | MICHAEL SOTO |
| Grading Pre-Inspection | Cleared | 3/9/2023 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 3/19/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2023 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 10/17/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 10/17/2023 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/19/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 10/19/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 10/19/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/24/2023 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 10/24/2023 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 10/24/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/14/2023 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 11/14/2023 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Rough | 11/14/2023 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 11/14/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/30/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 11/30/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 11/30/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/8/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/8/2024 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 3/6/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 3/6/2024 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 3/6/2024 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/8/2024 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 3/8/2024 | Approved | FREDDIE RIVERA |
| Insulation | 3/15/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | JOSH MEISTER |
| Drywall Nailing | 7/9/2024 | Approved | FREDDIE RIVERA |
| Shower Pan | 7/9/2024 | Approved | FREDDIE RIVERA |
| Final | 12/20/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 12/20/2024 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 12/20/2024 | Approved | FREDDIE RIVERA |
| Final | 1/14/2025 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Final | 1/14/2025 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 2/19/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 2/19/2025 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 3/3/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 3/3/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | FREDDIE RIVERA |