1447 S WESTGATE AVE 1-9 90025

Certificate Information: 1447 S WESTGATE AVE 1-9 90025

Application / Permit
22016-10000-38946
Plan Check / Job No.
B22LA26250
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan CONVERT EXISTING CARPORT TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 6/14/2023
Issuing Office
Current Status
CofO Issued on 8/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/3/2023 FARSHAD ALIMOHAMADI
Corrections Issued 1/4/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/10/2023 DANIEL YIP
Applicant returned to address corrections 3/9/2023 DANIEL YIP
Plan Check Approved 6/12/2023 MICHAEL LOPEZ
Issued 6/14/2023 APPLICANT
CofO in Progress 8/21/2024 CASIMIR BRITTON
Permit Finaled 8/27/2024 DAVID TSAU
Permit Finaled 8/27/2024 DAVID TSAU
CofO Issued 8/27/2024 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 1/11/2023 JENSON LEE
Sewer availability Cleared 1/11/2023 JENSON LEE
"Q" conditions Cleared 1/12/2023 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 1/13/2023 JENSON LEE
ZI Cleared 1/13/2023 BRENNEN OBETO
Specific Plan Cleared 1/31/2023 VALERIA CEJA
Tenant Habitability Plan Cleared 2/6/2023 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2023 Partial Inspection SORIN CIRSTOIU
Pre-Inspection 9/7/2023 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 9/11/2023 Conditional Approval AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 9/12/2023 Conditional Approval GRANT WOODS
Green Building Rough 10/13/2023 Approved MICHAEL PETRUSKO
Wood Frame 10/13/2023 Approved MICHAEL PETRUSKO
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 10/20/2023 Conditional Approval MICHAEL PETRUSKO
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved MICHAEL PETRUSKO
Insulation 11/7/2023 Approved CASIMIR BRITTON
Drywall Nailing 11/13/2023 Partial Approval CASIMIR BRITTON
Interior/Exterior Lathing 12/11/2023 Approved CASIMIR BRITTON
Interior/Exterior Lathing 1/9/2024 No Access for Inspection CASIMIR BRITTON
Interior/Exterior Lathing 1/10/2024 Partial Approval CASIMIR BRITTON
Deputy Wood Construction 3/21/2024 Conditional Approval CASIMIR BRITTON
Deputy Wood Construction 4/23/2024 Approved CASIMIR BRITTON
Final 7/15/2024 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 7/15/2024 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 7/15/2024 Not Ready for Inspection CASIMIR BRITTON
Special/Order Compliance 7/16/2024 Corrections Issued CASIMIR BRITTON
Special/Order Compliance 7/18/2024 Corrections Issued CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Not Ready CASIMIR BRITTON
Final 7/23/2024 Not Ready for Inspection CASIMIR BRITTON
Final 7/31/2024 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 7/31/2024 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 7/31/2024 Approved CASIMIR BRITTON
Interior/Exterior Lathing 8/6/2024 Approved MICHAEL PETRUSKO
Final 8/14/2024 Not Ready for Inspection CASIMIR BRITTON
Final 8/21/2024 OK to Issue CofO CASIMIR BRITTON