1447 S WESTGATE AVE 1-9 90025
Certificate Information: 1447 S WESTGATE AVE 1-9 90025
- Application / Permit
- 22016-10000-38946
- Plan Check / Job No.
- B22LA26250
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan CONVERT EXISTING CARPORT TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- CofO Issued on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/4/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/10/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/9/2023 | DANIEL YIP |
| Plan Check Approved | 6/12/2023 | MICHAEL LOPEZ |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 8/21/2024 | CASIMIR BRITTON |
| Permit Finaled | 8/27/2024 | DAVID TSAU |
| Permit Finaled | 8/27/2024 | DAVID TSAU |
| CofO Issued | 8/27/2024 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2023 | JENSON LEE |
| Sewer availability | Cleared | 1/11/2023 | JENSON LEE |
| "Q" conditions | Cleared | 1/12/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2023 | JENSON LEE |
| ZI | Cleared | 1/13/2023 | BRENNEN OBETO |
| Specific Plan | Cleared | 1/31/2023 | VALERIA CEJA |
| Tenant Habitability Plan | Cleared | 2/6/2023 | MICHAEL SOTO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2023 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 9/7/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 9/11/2023 | Conditional Approval | AMANUEL BERHE |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Conditional Approval | GRANT WOODS |
| Green Building Rough | 10/13/2023 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 10/13/2023 | Approved | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Wood Construction | 10/20/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | MICHAEL PETRUSKO |
| Insulation | 11/7/2023 | Approved | CASIMIR BRITTON |
| Drywall Nailing | 11/13/2023 | Partial Approval | CASIMIR BRITTON |
| Interior/Exterior Lathing | 12/11/2023 | Approved | CASIMIR BRITTON |
| Interior/Exterior Lathing | 1/9/2024 | No Access for Inspection | CASIMIR BRITTON |
| Interior/Exterior Lathing | 1/10/2024 | Partial Approval | CASIMIR BRITTON |
| Deputy Wood Construction | 3/21/2024 | Conditional Approval | CASIMIR BRITTON |
| Deputy Wood Construction | 4/23/2024 | Approved | CASIMIR BRITTON |
| Final | 7/15/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Green Building Final | 7/15/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 7/15/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Special/Order Compliance | 7/16/2024 | Corrections Issued | CASIMIR BRITTON |
| Special/Order Compliance | 7/18/2024 | Corrections Issued | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Not Ready | CASIMIR BRITTON |
| Final | 7/23/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 7/31/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Green Building Final | 7/31/2024 | Approved | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 7/31/2024 | Approved | CASIMIR BRITTON |
| Interior/Exterior Lathing | 8/6/2024 | Approved | MICHAEL PETRUSKO |
| Final | 8/14/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 8/21/2024 | OK to Issue CofO | CASIMIR BRITTON |