1714 N WESTRIDGE ROAD 90049
Certificate Information: 1714 N WESTRIDGE ROAD 90049
- Application / Permit
- 22016-10000-38904
- Plan Check / Job No.
- B22LA26194
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF KITCHEN TO OPEN INTO DINING/ LIVING ROOM, ADD A POWDER ROOM, SKYLIGHTS, PAD FOOTINGS, COLUMNS, AND PSL BEAM. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/7/2023
Permit Application Status History
| Submitted | 12/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2022 | MADISON ODELL |
| Corrections Issued | 3/3/2023 | MADISON ODELL |
| Plan Check Approved | 3/10/2023 | MADISON ODELL |
| Issued | 3/10/2023 | APPLICANT |
| Permit Finaled | 7/6/2023 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/2/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Caliper Design-Build Co Llc; Lic. No.: 1075113-B | , |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/14/2023 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 3/14/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 3/17/2023 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 3/17/2023 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/21/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/28/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/28/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 3/31/2023 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/31/2023 | No Access for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/6/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 4/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/6/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/11/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 4/14/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 4/21/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/2/2023 | Approved | KEVIN SARGSYAN |
| Final | 6/26/2023 | Corrections Issued | KENNETH NAGLE |
| HVAC-Final | 6/26/2023 | Approved | KENNETH NAGLE |
| PLUMBING-Final | 6/26/2023 | Approved | KENNETH NAGLE |
| Final | 7/6/2023 | Permit Finaled | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/6/2023 | Approved | KEVIN SARGSYAN |