2535 E 12TH ST B 90023

Certificate Information: 2535 E 12TH ST B 90023

Application / Permit
22016-10000-38870
Plan Check / Job No.
B22LA26152
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
ePlan THE SCOPE OF THIS PROJECT IS TO DEMO EXISTING OFFICE AND MEZZANINE SPACES ALONG WITH STAIRS AND RESTROOMS. PROVIDE NEW OFFICE SPACE ON FIRST AND MEZZANINE AREAS ALONG WITH NEW RESTROOMS, STAIRS AND BREAKROOM AREAS. REMOVE ALL WAREHOUSE LIGHTING FIXTURES AND PROVIDE NEW LED FIXTURES.
Permit Issued
Issued on 4/12/2023
Issuing Office
Current Status
Issued on 4/12/2023

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 ARSALAN SHABESTARI
Corrections Issued 1/14/2023 ARSALAN SHABESTARI
Quality Review Completed 1/18/2023 GARO TELMI
Applicant returned to address corrections 3/13/2023 ARSALAN SHABESTARI
Plan Check Approved 3/17/2023 ARSALAN SHABESTARI
Issued 4/12/2023 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 2/17/2023 TREVOR QUAN
Green Code Cleared 2/24/2023 Hernan Arreola
DAS Clearance Cleared 2/28/2023 Hernan Arreola
Eng Process Fee Ord 176,300 Cleared 2/28/2023 TREVOR QUAN

Contact Information

Contractor Coastal Pacific Construction Inc; Lic. No.: 478584-B       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 6/26/2023 Approved JULIAN CAPUCETTI
Footing/Foundation/Slab 6/26/2023 Partial Approval JULIAN CAPUCETTI
Wood Frame 6/28/2023 Partial Approval JULIAN CAPUCETTI
Light Gage Steel Frame 7/25/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 8/1/2023 Partial Approval JULIAN CAPUCETTI
Insulation 8/1/2023 Partial Approval JULIAN CAPUCETTI
Excavation/Setback/Form/Re-Bar 8/3/2023 Partial Approval ALAN MORELOS
Deputy Steel/Welding 8/14/2023 Conditional Approval JULIAN CAPUCETTI
Pre-Inspection 9/14/2023 Approved ALAN MORELOS
Pre-Inspection 9/15/2023 No Access for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/12/2023 Approved RAMAZANALI ALMASI
Deputy Reinf. Concrete 10/13/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 10/26/2023 Partial Approval RICARDO ROBLES
Final 1/4/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 1/4/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 1/4/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 1/19/2024 Corrections Issued RAFAEL CORTES
Green Building Final 1/19/2024 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 1/19/2024 Approved RAFAEL CORTES
Final 1/22/2024 Not Ready for Inspection RICARDO ROBLES