11601 W WILSHIRE BLVD 90025

Certificate Information: 11601 W WILSHIRE BLVD 90025

Application / Permit
22016-10000-38788
Plan Check / Job No.
B22LA26069
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
eplan New Tenant Improvement at level 8, 9, and 10 include: CORE RESTROOMS, ONE TERRACE AT LEVEL 8, NON-BEARING PARTITIONS, MILLWORK, CEILING SYSTEM & LIGHTING, DOORS & FRAMES, FIXTURES & FURNITURE SYSTEMS, CARPET & PAINT FINISHES. LEVEL 8, 9, & 10.
Permit Issued
Issued on 12/4/2023
Issuing Office
Current Status
Permit Finaled on 2/11/2026

Permit Application Status History

Submitted 12/23/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2023 NGHI SU
Corrections Issued 1/19/2023 NGHI SU
Quality Review Completed 1/25/2023 GARO TELMI
Applicant returned to address corrections 10/11/2023 NGHI SU
Plan Check Approved 10/26/2023 NGHI SU
Issued 12/4/2023 APPLICANT
Permit Finaled 2/10/2026 CASIMIR BRITTON

Permit Application Clearance Information

Sewer availability Cleared 2/8/2023 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 2/22/2023 CATHERINE ADROVER
Fire Marshal Fire Life Safety Cleared 2/26/2023 MENOA AGHAJANI
Supp. Use District POD/CDO/TDO Cleared 7/19/2023 NGHI SU
Green Code Cleared 8/3/2023 AARON COSTA
DAS Clearance Cleared 9/14/2023 Luke Gonzales
Hold Cleared 4/16/2025 SANDRA SOH

Contact Information

Architect Young,, Alan Thomas; Lic. No.: C34719 500 S FIGUEROA STREET      LOS ANGELES, CA 90071
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,
Engineer Smith,, Chris Wayne; Lic. No.: S6106 1852 CORINTH AVE #11      LOS ANGELES, CA 90025

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Fireproofing 4/18/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 4/18/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 4/21/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 4/22/2025 Conditional Approval CASIMIR BRITTON
Light Gage Steel Frame 4/22/2025 Partial Approval CASIMIR BRITTON
Deputy Steel/Welding 4/23/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 4/24/2025 Conditional Approval CASIMIR BRITTON
Drywall Nailing 4/24/2025 Not Ready for Inspection CASIMIR BRITTON
Insulation 4/24/2025 Partial Approval CASIMIR BRITTON
Deputy Steel/Welding 4/25/2025 Conditional Approval CASIMIR BRITTON
Drywall Nailing 4/30/2025 Approved VASIL MIHALEV
Deputy Steel/Welding 5/2/2025 Approved VASIL MIHALEV
Deputy Steel/Welding 5/5/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 5/7/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 5/12/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 5/13/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 5/14/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 5/15/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 5/16/2025 Conditional Approval CASIMIR BRITTON
Green Building Rough 5/22/2025 Approved CASIMIR BRITTON
Insulation 5/22/2025 Partial Approval CASIMIR BRITTON
Light Gage Steel Frame 6/6/2025 Partial Approval CASIMIR BRITTON
Deputy Fireproofing 6/10/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 6/10/2025 Conditional Approval CASIMIR BRITTON
Deputy Steel/Welding 6/12/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/16/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/17/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/18/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/20/2025 Conditional Approval DANIEL VARNUM
Insulation 6/23/2025 Partial Inspection CASIMIR BRITTON
Structural Steel Frame 6/23/2025 Partial Inspection CASIMIR BRITTON
Deputy Fireproofing 6/24/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/25/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/26/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/27/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 6/30/2025 Conditional Approval PAUL DAVIDSON
Deputy Fireproofing 7/1/2025 Conditional Approval DANIEL VARNUM
Deputy Fireproofing 7/2/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 7/3/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 7/11/2025 Conditional Approval CASIMIR BRITTON
Deputy Fireproofing 8/7/2025 Conditional Approval CASIMIR BRITTON
Drywall Nailing 8/20/2025 Partial Approval CASIMIR BRITTON
T-Bar Ceiling 9/16/2025 Partial Approval CASIMIR BRITTON
Final 10/10/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 10/10/2025 Not Ready for Inspection CASIMIR BRITTON
METHANE-Final 10/10/2025 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 10/10/2025 Not Ready for Inspection CASIMIR BRITTON
Final 2/10/2026 Permit Finaled CASIMIR BRITTON
Green Building Final 2/10/2026 Approved CASIMIR BRITTON
METHANE-Final 2/10/2026 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 2/10/2026 Approved CASIMIR BRITTON