2862 S ANCHOR AVE 90064
Certificate Information: 2862 S ANCHOR AVE 90064
- Application / Permit
- 22016-10000-38786
- Plan Check / Job No.
- B22LA26068
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan MAJOR EXTERIOR AND INTERIOR REMODEL OF SFD
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/21/2024
Permit Application Status History
| Submitted | 12/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | SUNMIN LEE |
| Corrections Issued | 12/27/2022 | SUNMIN LEE |
| Plan Check Approved | 1/20/2023 | ADAM HEGAZI |
| Issued | 1/23/2023 | APPLICANT |
| Permit Finaled | 6/21/2024 | SEAN HAUPT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 12/27/2022 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 1/4/2023 | KIRK LINKLATER |
Contact Information
| Architect | Miller,, Alexander Ryan; Lic. No.: C34164 | 9187 CLAIRMONT MESA BLVD #6-743 SAN DIEGO, CA 92123 |
| Contractor | Owner-Builder | , |
| Engineer | Neth,, George King; Lic. No.: S3837 | PO BOX 429 MI-WUK VILLAGE, CA 95346 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/16/2023 | Corrections Issued | DAVID FEILER |
| Pre-Inspection | 8/16/2023 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 10/10/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 10/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| Pre-Inspection | 10/18/2023 | Partial Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 10/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 10/24/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 10/25/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 11/2/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 11/2/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 11/2/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 11/6/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/6/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 11/22/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 11/30/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/8/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 1/3/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/26/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 4/26/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 4/26/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/26/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/26/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 6/21/2024 | Permit Finaled | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Approved | SEAN HAUPT |