3840 W BRUNSWICK AVE 90039
Certificate Information: 3840 W BRUNSWICK AVE 90039
- Application / Permit
- 22016-10000-38728
- Plan Check / Job No.
- B22LA25978
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: MAJOR INTERIOR REMODEL TO RECONFIGURE ENTIRE FLOOR PLAN LAYOUT AND EXPAND 2ND FLOOR MEZZANINE. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 1/7/2023 | GURUNATH NESARAJAH |
| Quality Review Completed | 1/11/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/23/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/9/2023 | GURUNATH NESARAJAH |
| Issued | 4/28/2023 | APPLICANT |
| CofO in Progress | 12/28/2023 | HAMIK HARTOUNIAN |
| CofO Issued | 12/29/2023 | DEROLD HAUFF |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/6/2023 | JEANIE LAM |
| ZI | Cleared | 2/7/2023 | DANIEL CORONADO |
Contact Information
| Architect | Tazedjian, Reistetter, Carolina S; Lic. No.: C32687 | 1716 PUTNEY ROAD PASADENA, CA 91103 |
| Architect | Tazedjian, Reistetter, Carolina S; Lic. No.: NA32687 | , |
| Contractor | Highground Builders; Lic. No.: 1042579-B | , |
| Contractor | Highground Solutions Inc.; Lic. No.: 1042579-B | , |
| Engineer | Tang,, Long Thanh; Lic. No.: C74481 | 5436 CADBURY RD WHITTIER, CA 90601 |
| Engineer | Tang,, Long Thanh; Lic. No.: NA74481 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/3/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/4/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 6/26/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/14/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/15/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/22/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 8/22/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/29/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/29/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/18/2023 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 9/18/2023 | Approved | JOSH MEISTER |
| Insulation | 9/22/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/28/2023 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 9/28/2023 | Approved | KATHRYN BUTTERWORTH |
| Final | 12/13/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 12/13/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/13/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 12/28/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |