1024 N ORANGE DR 90038

Certificate Information: 1024 N ORANGE DR 90038

Application / Permit
22016-10000-38701
Plan Check / Job No.
B22LA25948
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePlan Eplan RETROFIT EXISTING 2 STORY URM STRUCTURE PER DIVISION 88 URM ORDINANCE WITH HAZARD CLASS III-C RATING. NEW CORE AND SHELL SCOPE WILL SEISMICALLY UPGRADE TO HAZARD CLASS II RATING PER APPENDIX A1 OF CEBC. TENANT IMPROVEMENT DESIGN SCOPE IS NOT PART OF CORE AND SHELL PACKAGE, HOWEVER ANY ALTERATIONS AND ADDITIONAL SEISMIC WEIGHT FROM TENANT IMPROVEMENT SCOPE ARE CONSIDERED WITHIN CORE AND SHELL SEISMIC UPGRADE
Permit Issued
Issued on 5/3/2023
Issuing Office
Current Status
Permit Finaled on 4/17/2024

Permit Application Status History

Submitted 12/26/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 SERGIO GUTIERREZ
Corrections Issued 1/23/2023 SERGIO GUTIERREZ
Quality Review Completed 1/27/2023 RODOLFO ARIAS
Applicant returned to address corrections 3/6/2023 SERGIO GUTIERREZ
Applicant returned to address corrections 3/23/2023 SERGIO GUTIERREZ
Plan Check Approved 4/27/2023 SERGIO GUTIERREZ
Issued 5/3/2023 APPLICANT
Permit Finaled 4/16/2024 MARTIN TAVITIAN

Permit Application Clearance Information

ZI Cleared 1/30/2023 MAXFIELD VERMY
Fire Marshal Fire Life Safety Cleared 3/22/2023 DOMINIQUE MEDINA
Green Code Cleared 4/5/2023 Samuel Gonzalez
DAS Clearance Cleared 4/6/2023 Samuel Gonzalez

Contact Information

Architect Lantz,, Andrew; Lic. No.: C38831 510 TAMARAC DRIVE      PASADENA, CA 91105
Contractor Corporate Contractors Inc; Lic. No.: 604407-B 2550 CORPORATE PL STE C-111      MONTEREY PARK, CA 91754
Engineer Wilkerson,, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/18/2023 Partial Approval JEROME BLACKWOOD
Deputy Drilled-In Anchors 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/22/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/24/2023 Partial Approval JEROME BLACKWOOD
Masonry Wall/Backfill 5/24/2023 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Masonry 5/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/1/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 6/1/2023 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Masonry 6/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/5/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 6/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/12/2023 No Access for Inspection ALFREDO LOPEZ
Deputy Drilled-In Anchors 6/14/2023 Conditional Approval MICHAEL ROSENBERG
Wall Anchors 6/15/2023 Partial Inspection GREGORY POMISH
Wood Frame 6/15/2023 Not Ready for Inspection GREGORY POMISH
Deputy Drilled-In Anchors 6/21/2023 Conditional Approval MICHAEL ROSENBERG
Wood Frame 7/24/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/4/2024 Conditional Approval RICARDO ROBLES
Final 3/21/2024 Partial Inspection JACOB MYERS
Green Building Final 3/21/2024 Not Ready for Inspection JACOB MYERS
SGSOV-Seismic Gas S/O Valve 3/21/2024 SGSOV No Gas JACOB MYERS
Smoke Detectors 3/21/2024 Partial Inspection JACOB MYERS
Final 4/16/2024 Permit Finaled MARTIN TAVITIAN
Green Building Final 4/16/2024 Approved MARTIN TAVITIAN
Smoke Detectors 4/16/2024 Approved MARTIN TAVITIAN