1100 S GLENDON AVE STE 700 90024
Certificate Information: 1100 S GLENDON AVE STE 700 90024
- Application / Permit
- 22016-10000-38505
- Plan Check / Job No.
- B22LA25715
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePLAN- OFFICE INTERIOR TENANT IMPROVEMENT: SELECTIVE DEMOLITION AND CONSTRUCTION OF NON-LOAD BEARING WALLS, CEILINGS, FINISHES, MILLWORK, MECHANICAL, ELECTRICAL, LIGHTING, PLUMBING AND FURNITURE.
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/25/2025
Permit Application Status History
| Submitted | 12/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2022 | ZAW HAN |
| Plan Check Approved | 1/2/2023 | ZAW HAN |
| Issued | 11/19/2024 | APPLICANT |
| Permit Finaled | 8/25/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | De, Valeria, David Alan; Lic. No.: C21877 | 1931 DIAMOND STREET APT 1 SAN FRANCISCO, CA 94131 |
| Architect | De, Valeria, David Alan; Lic. No.: NA21877 | , |
| Contractor | Bcci Construction Llc; Lic. No.: 492944-B | 1160 BATTERY STREET 250 SAN FRANCISCO, CA 94111 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2025 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 2/18/2025 | Partial Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 2/20/2025 | Partial Inspection | AMANUEL BERHE |
| Insulation | 2/21/2025 | Approved | RICARDO ROBLES |
| Light Gage Steel Frame | 2/21/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 2/27/2025 | Conditional Approval | AMANUEL BERHE |
| Deputy Steel/Welding | 2/27/2025 | Conditional Approval | AMANUEL BERHE |
| Drywall Nailing | 3/6/2025 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 4/23/2025 | Partial Inspection | RICARDO ROBLES |
| Drywall Nailing | 4/25/2025 | Approved | VASIL MIHALEV |
| Drywall Nailing | 5/2/2025 | Partial Approval | FARHAD DADBIN |
| T-Bar Ceiling | 5/13/2025 | No Access for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 5/14/2025 | Not Ready for Inspection | RICARDO ROBLES |
| T-Bar Ceiling | 6/20/2025 | Approved | PAUL DAVIDSON |
| Pre-Inspection | 7/25/2025 | Partial Inspection | DANIEL VARNUM |
| Final | 8/25/2025 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 8/25/2025 | Approved | FARHAD DADBIN |