5419-5419 1/2 E BUCHANAN ST 90042
Certificate Information: 5419-5419 1/2 E BUCHANAN ST 90042
- Application / Permit
- 22016-10000-38495
- Plan Check / Job No.
- B22LA25705
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE CONVERT A PORTION OF EXISITING SFD INTO NEW ATTACHED ADU (1150sqft) PER STATE LAW
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2022 | ZAW HAN |
| Corrections Issued | 12/27/2022 | ZAW HAN |
| Building Plans Picked Up | 5/23/2023 | APPLICANT |
| Plan Check Approved | 9/19/2023 | KHUONG TRUONG |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/1/2024 | DEROLD HAUFF |
| CofO Issued | 5/1/2024 | DEROLD HAUFF |
| Permit Finaled | 5/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 3/17/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 3/17/2023 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 6/15/2023 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2023 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/8/2023 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 12/8/2023 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 12/8/2023 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/21/2023 | Partial Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 12/21/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/21/2023 | Approved | ROY SPAULDING |
| Insulation | 12/28/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/10/2024 | Approved | ROY SPAULDING |
| Insulation | 1/10/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 1/19/2024 | Approved | ROY SPAULDING |
| Final | 4/19/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/19/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/24/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/24/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/1/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |