1071 S POINT VIEW ST 90035
Certificate Information: 1071 S POINT VIEW ST 90035
- Application / Permit
- 22016-10000-38455
- Plan Check / Job No.
- B22LA25647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN - MAKE 2 INTERIOR OPENING WIDER, - ADD FRENCH DOOR TO THE BEDROOM - NO ADDITION ON FLOOR AREA - NO ADDITION ON HEIGHT - NO CHANGE ON EXTERIOR FECADE FACING STREET
- Permit Issued
- Issued on 2/1/2023
- Issuing Office
- Current Status
- Permit Finaled on 9/5/2023
Permit Application Status History
| Submitted | 12/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2022 | ZAW HAN |
| Corrections Issued | 12/28/2022 | ZAW HAN |
| Plan Check Approved | 1/27/2023 | ZAW HAN |
| Issued | 2/1/2023 | APPLICANT |
| Permit Finaled | 9/5/2023 | RUBEN PEREZ |
Permit Application Clearance Information
| CPC | Cleared | 1/3/2023 | JONATHAN KAPLAN |
| City Hist. Cultural Monument | Cleared | 1/3/2023 | JONATHAN KAPLAN |
| HPOZ | Cleared | 1/3/2023 | JONATHAN KAPLAN |
| Historic monument | Cleared | 1/3/2023 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 1/3/2023 | JONATHAN KAPLAN |
Contact Information
| Architect | , ; Lic. No.: C35150 | , |
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/15/2023 | Corrections Issued | JOHN TCHANG |
| Excavation/Setback/Form/Re-Bar | 2/27/2023 | Partial Approval | JOHN TCHANG |
| BUILDING-Rough-Frame | 3/7/2023 | Approved | JOHN TCHANG |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Approved | JOHN TCHANG |
| Drywall Nailing | 3/14/2023 | Approved | ROBERT CHAVEZ |
| Interior/Exterior Lathing | 3/14/2023 | Approved | ROBERT CHAVEZ |
| Final | 6/16/2023 | No Access for Inspection | RUBEN PEREZ |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Not Ready | RUBEN PEREZ |
| Smoke Detectors | 6/16/2023 | No Access for Inspection | RUBEN PEREZ |
| Final | 6/21/2023 | Corrections Issued | RUBEN PEREZ |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | RUBEN PEREZ |
| Smoke Detectors | 6/21/2023 | Approved | RUBEN PEREZ |
| Final | 7/5/2023 | Corrections Issued | RUBEN PEREZ |
| Pre-Inspection | 7/7/2023 | Approved | RUBEN PEREZ |
| Final | 9/5/2023 | Permit Finaled | RUBEN PEREZ |