1071 S POINT VIEW ST 90035

Certificate Information: 1071 S POINT VIEW ST 90035

Application / Permit
22016-10000-38455
Plan Check / Job No.
B22LA25647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN - MAKE 2 INTERIOR OPENING WIDER, - ADD FRENCH DOOR TO THE BEDROOM - NO ADDITION ON FLOOR AREA - NO ADDITION ON HEIGHT - NO CHANGE ON EXTERIOR FECADE FACING STREET
Permit Issued
Issued on 2/1/2023
Issuing Office
Current Status
Permit Finaled on 9/5/2023

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 12/27/2022 ZAW HAN
Corrections Issued 12/28/2022 ZAW HAN
Plan Check Approved 1/27/2023 ZAW HAN
Issued 2/1/2023 APPLICANT
Permit Finaled 9/5/2023 RUBEN PEREZ

Permit Application Clearance Information

CPC Cleared 1/3/2023 JONATHAN KAPLAN
City Hist. Cultural Monument Cleared 1/3/2023 JONATHAN KAPLAN
HPOZ Cleared 1/3/2023 JONATHAN KAPLAN
Historic monument Cleared 1/3/2023 JONATHAN KAPLAN
Miscellaneous Cleared 1/3/2023 JONATHAN KAPLAN

Contact Information

Architect , ; Lic. No.: C35150       ,
Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2023 Corrections Issued JOHN TCHANG
Excavation/Setback/Form/Re-Bar 2/27/2023 Partial Approval JOHN TCHANG
BUILDING-Rough-Frame 3/7/2023 Approved JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved JOHN TCHANG
Drywall Nailing 3/14/2023 Approved ROBERT CHAVEZ
Interior/Exterior Lathing 3/14/2023 Approved ROBERT CHAVEZ
Final 6/16/2023 No Access for Inspection RUBEN PEREZ
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Not Ready RUBEN PEREZ
Smoke Detectors 6/16/2023 No Access for Inspection RUBEN PEREZ
Final 6/21/2023 Corrections Issued RUBEN PEREZ
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved RUBEN PEREZ
Smoke Detectors 6/21/2023 Approved RUBEN PEREZ
Final 7/5/2023 Corrections Issued RUBEN PEREZ
Pre-Inspection 7/7/2023 Approved RUBEN PEREZ
Final 9/5/2023 Permit Finaled RUBEN PEREZ