22020-22022 S DENKER AVE 90501

Certificate Information: 22020-22022 S DENKER AVE 90501

Application / Permit
22016-10000-38448
Plan Check / Job No.
B22LA25640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERTING EXISTING 4 CAR GARAGE TO 2 ADU'S 405 SQ. FT. EACH PER STATE LAW "CONSTRUCTION TO DRIVEWAYS / SIDEWALKS / CURB & GUTTER" CLEARANCE TO CLOSE (E) DWY APRON LEADING INTO PROPOSED ADUs***
Permit Issued
Issued on 4/5/2023
Issuing Office
Current Status
Issued on 4/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/3/2023 DANIEL SANJUAN
Corrections Issued 1/4/2023 DANIEL SANJUAN
Applicant returned to address corrections 1/17/2023 JOSEPH RAFOLS
Plan Check Approved 1/30/2023 JOSEPH RAFOLS
Issued 4/5/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/5/2023 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/5/2023 ERIK BEASLEY
Sewer availability Cleared 1/5/2023 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: NA41697       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/16/2023 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/28/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/3/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/24/2023 Approved EUGENE CASSIDY
Gas Test 8/24/2023 Approved EUGENE CASSIDY
HVAC-Rough 8/24/2023 Approved EUGENE CASSIDY
Wood Frame 8/30/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/31/2023 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 9/8/2023 Approved EUGENE CASSIDY
Deputy Wood Construction 9/8/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/12/2023 Partial Approval EUGENE CASSIDY
Insulation 9/18/2023 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/27/2023 Approved EUGENE CASSIDY
Special/Order Compliance 9/27/2023 Approved EUGENE CASSIDY
Sewer 10/3/2023 Approved EUGENE CASSIDY
Underground Mechanical 10/3/2023 Approved EUGENE CASSIDY
Drywall Nailing 10/5/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/27/2023 Approved EUGENE CASSIDY
Final 2/8/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 2/8/2024 Not Ready for Inspection EUGENE CASSIDY
Final 2/28/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/28/2024 Approved EUGENE CASSIDY
Final 4/14/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 6/11/2025 Approved EUGENE CASSIDY
Special/Order Compliance 6/11/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 1/22/2026 Approved EUGENE CASSIDY
Final 1/22/2026 Corrections Issued EUGENE CASSIDY
HVAC-Final 1/22/2026 Approved EUGENE CASSIDY
PLUMBING-Final 1/22/2026 Approved EUGENE CASSIDY
PLUMBING-Rough 1/22/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/19/2026 Approved EUGENE CASSIDY
Final 3/19/2026 Corrections Issued EUGENE CASSIDY
Gas Test 3/19/2026 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 3/19/2026 Approved EUGENE CASSIDY
PLUMBING-Final 3/19/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/1/2026 Approved EUGENE CASSIDY
Final 6/1/2026 Corrections Issued EUGENE CASSIDY
HVAC-Final 6/1/2026 Approved EUGENE CASSIDY
PLUMBING-Final 6/1/2026 Approved EUGENE CASSIDY