501 S HARVARD BLVD 90020
Certificate Information: 501 S HARVARD BLVD 90020
- Application / Permit
- 22016-10000-38280
- Plan Check / Job No.
- B22LA25542
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story Seismic Retrofit per LABC Chapter 93: Install Two (2) Special Steel Cantilever Columns
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/7/2026
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | BIDYUT RATH |
| Corrections Issued | 1/27/2023 | BIDYUT RATH |
| Quality Review Completed | 2/6/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/24/2023 | BIDYUT RATH |
| Plan Check Approved | 3/30/2023 | BIDYUT RATH |
| Issued | 6/6/2023 | APPLICANT |
| Permit Finaled | 1/7/2026 | DARRYL ARNOLD |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/16/2023 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 3/16/2023 | GRACIELA ACOSTA |
| Tenant Habitability Plan | Cleared | 5/10/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/25/2023 | Partial Inspection | VAHE KELEDJIAN |
| Pre-Inspection | 7/26/2023 | Corrections Issued | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 11/1/2023 | Approved | JACOB MYERS |
| Structural Steel Frame | 11/1/2023 | Partial Approval | JACOB MYERS |
| Wood Frame | 11/1/2023 | Corrections Issued | JACOB MYERS |
| Special/Order Compliance | 11/3/2023 | Order to Comply Issued | JACOB MYERS |
| Pre-Inspection | 11/15/2023 | Corrections Issued | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 3/6/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/27/2024 | Approved | JACOB MYERS |
| Final | 4/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/18/2024 | Corrections Issued | DARRYL ARNOLD |
| Final | 5/6/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/6/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 5/9/2024 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/9/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 1/7/2026 | Permit Finaled | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 1/7/2026 | Approved | DARRYL ARNOLD |