4913-4913 1/2 E LYNNFIELD ST 90032

Certificate Information: 4913-4913 1/2 E LYNNFIELD ST 90032

Application / Permit
22016-10000-38226
Plan Check / Job No.
B22LA25527
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF EXISTING CRAWL SPACE IN EXISTING SINGLE FAMILY DWELLING TO A JADU (495 SQFT) AND A STORAGE ROOM (150 SQFT)
Permit Issued
Issued on 10/17/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 JAD BASMA
Corrections Issued 1/9/2023 JAD BASMA
Quality Review Completed 1/13/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/19/2023 APPLICANT
Applicant returned to address corrections 10/5/2023 JAD BASMA
Plan Check Approved 10/11/2023 JAD BASMA
Issued 10/17/2023 APPLICANT
CofO in Progress 2/7/2025 LILIANA PORTILLO
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/1/2023 STEVE MELGAR
Sewer availability Cleared 3/1/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/14/2023 STEVE MELGAR
"D" conditions Cleared 6/29/2023 DAVID URITA
"Q" conditions Cleared 6/29/2023 DAVID URITA
Grading Pre-Inspection Cleared 10/5/2023 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/19/2023 Corrections Issued OSVALDO PARAMO
Pre-Inspection 10/31/2023 Not Ready for Inspection AMY COLIN
Pre-Inspection 11/9/2023 Partial Inspection SCOTT FINNILA
Pre-Inspection 11/16/2023 Approved ROY SPAULDING
Pre-Inspection 11/28/2023 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 12/4/2023 Corrections Issued SCOTT FINNILA
Final 1/27/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 1/27/2025 Not Ready for Inspection LILIANA PORTILLO
Wood Frame 1/27/2025 Corrections Issued LILIANA PORTILLO
Final 1/30/2025 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 1/30/2025 Not Ready for Inspection LILIANA PORTILLO
Wood Frame 1/30/2025 Corrections Issued LILIANA PORTILLO
Final 2/4/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 2/4/2025 Approved LILIANA PORTILLO
Wood Frame 2/4/2025 Not Ready for Inspection LILIANA PORTILLO
Final 2/6/2025 OK to Issue CofO LILIANA PORTILLO
Wood Frame 2/6/2025 Approved LILIANA PORTILLO