11848 W BEL TER 90049

Certificate Information: 11848 W BEL TER 90049

Application / Permit
22016-10000-38186
Plan Check / Job No.
B22LA25508
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan :Remove three none load bearing walls and make the master bathroom bigger, change two windows to sliding doors with the same width, No change to headers. Add sink to kitchen island. Bathroom and kitchen remodel.
Permit Issued
Issued on 12/28/2022
Issuing Office
Current Status
Permit Finaled on 9/1/2023

Permit Application Status History

Submitted 12/19/2022 APPLICANT
Assigned to Plan Check Engineer 12/19/2022 RICARDO RAMIREZ
Plan Check Approved 12/20/2022 RICARDO RAMIREZ
Issued 12/28/2022 APPLICANT
Permit Finaled 8/31/2023 CARLOS MATAMOROS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/9/2023 Corrections Issued CARLOS MATAMOROS
Gas Test 1/9/2023 Approved CARLOS MATAMOROS
HVAC-Rough 1/9/2023 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 1/9/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 1/9/2023 Approved CARLOS MATAMOROS
Underground Mechanical 1/9/2023 Approved CARLOS MATAMOROS
Underground Mechanical 1/20/2023 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 1/24/2023 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 2/2/2023 Partial Approval CARLOS MATAMOROS
Gas Test 2/2/2023 Approved CARLOS MATAMOROS
HVAC-Rough 2/2/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/2/2023 Corrections Issued CARLOS MATAMOROS
Wood Frame 2/2/2023 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 2/14/2023 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 2/14/2023 Approved CARLOS MATAMOROS
Underground Mechanical 2/14/2023 Approved CARLOS MATAMOROS
Wood Frame 2/14/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 2/24/2023 Approved CARLOS MATAMOROS
Insulation 2/24/2023 Approved CARLOS MATAMOROS
Shower Pan 2/24/2023 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 3/20/2023 Approved STEPHANIE SWANSON
Shower Pan 3/20/2023 Corrections Issued STEPHANIE SWANSON
Shower Pan 3/21/2023 Corrections Issued CARLOS MATAMOROS
Shower Pan 4/5/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/17/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 8/31/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/31/2023 Approved CARLOS MATAMOROS
Final 8/31/2023 Permit Finaled CARLOS MATAMOROS
HVAC-Final 8/31/2023 Approved CARLOS MATAMOROS
MERV13>=Final 8/31/2023 Approved CARLOS MATAMOROS
MERV13>=Rough 8/31/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 8/31/2023 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 8/31/2023 Approved CARLOS MATAMOROS