7150 W BEVERLY BLVD 90036

Certificate Information: 7150 W BEVERLY BLVD 90036

Application / Permit
22016-10000-38146
Plan Check / Job No.
B22LA25470
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
UNION OF ADJACENT RETAIL SPACE AND TAKE OUT RESTAURANT TO CHANGE OF USE FOR RESTAURANT. TI INCLUDES PARTITION WALLS, CEILINGS, MEP FOR (N) EQUIPMENT AS WELL AS TRADE FINISHES ON EXTERIOR W/ STORE FRONT MODIFICATION AND PATIO INSIDE BUILDING ENVELOPE
Permit Issued
Issued on 4/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 ARSALAN SHABESTARI
Corrections Issued 1/17/2023 ARSALAN SHABESTARI
Quality Review Completed 1/18/2023 KEN GILL
Building Plans Picked Up 1/20/2023 APPLICANT
Green Plans Picked Up 1/30/2023 APPLICANT
Disabled Access Plans Picked Up 2/27/2023 APPLICANT
Plan Check Approved 4/13/2023 ARSALAN SHABESTARI
Issued 4/14/2023 APPLICANT
CofO in Progress 10/13/2023 TED RIES
Permit Finaled 10/13/2023 TED RIES
CofO Issued 10/13/2023 TED RIES
Permit Finaled 10/13/2023 TED RIES

Permit Application Clearance Information

"D" conditions Cleared 1/25/2023 KENTON TRINH
CPC Cleared 1/25/2023 KENTON TRINH
ZA Case Cleared 1/25/2023 KENTON TRINH
Green Code Cleared 2/15/2023 MICHAEL MARTINEZ
Food Service Establishment Cleared 3/17/2023 RAMESHBHAIR PATEL
DAS Clearance Cleared 4/13/2023 ARSALAN SHABESTARI
Food establishment approval Cleared 4/13/2023 LACDHS APPROVED
Public Works-Open Permits Cleared 6/15/2023 NAZILA NOORIFAR

Contact Information

Contractor Ebs Construction Services Inc; Lic. No.: 973962-B P O BOX 822      TUSTIN, CA 92781

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2023 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Concrete 4/27/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 5/11/2023 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 5/17/2023 Partial Inspection ALFREDO LOPEZ
Wood Frame 5/17/2023 Partial Inspection ALFREDO LOPEZ
Insulation 5/24/2023 Approved ALFREDO LOPEZ
Drywall Nailing 5/31/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 6/5/2023 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 6/8/2023 Partial Approval MARTIN TAVITIAN
T-Bar Ceiling 6/21/2023 Not Ready for Inspection ALFREDO LOPEZ
T-Bar Ceiling 6/22/2023 Approved ALFREDO LOPEZ
Drywall Nailing 6/26/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 7/10/2023 Corrections Issued ALFREDO LOPEZ
T-Bar Ceiling 7/12/2023 Partial Approval JEROME BLACKWOOD
Final 9/28/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 9/28/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Not Required JEROME BLACKWOOD
Smoke Detectors 9/28/2023 Approved JEROME BLACKWOOD
Final 10/3/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 10/3/2023 Approved JEROME BLACKWOOD
Final 10/5/2023 Corrections Issued JEROME BLACKWOOD
Final 10/11/2023 OK to Issue CofO ALFREDO LOPEZ
Special/Order Compliance 10/12/2023 Conditional Approval JEROME BLACKWOOD