1218 S ST ANDREWS PL 90019

Certificate Information: 1218 S ST ANDREWS PL 90019

Application / Permit
22016-10000-37985
Plan Check / Job No.
B22LA25351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE INTO A.D.U WITH NEW ADDITIO. PER STATE LAW.
Permit Issued
Issued on 2/15/2023
Issuing Office
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2022 APPLICANT
Assigned to Plan Check Engineer 12/19/2022 LAWRENCE QUIRANTE
Corrections Issued 12/22/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 12/30/2022 APPLICANT
Plan Check Approved 2/15/2023 DANIEL SANJUAN
Issued 2/15/2023 APPLICANT
Permit Finaled 9/12/2024 CLAUDIO MORENO
CofO Issued 9/12/2024 CLAUDIO MORENO
Permit Finaled 9/12/2024 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 1/3/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/4/2023 TREVOR QUAN
Sewer availability Cleared 1/4/2023 TREVOR QUAN
HPOZ Cleared 1/27/2023 AMANDA KAINER

Contact Information

Contractor My Home Builders Inc; Lic. No.: 1002927-B 20720 VENTURA BLVD #280      WOODLAND HILLS, CA 91364
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2023 Corrections Issued GLEN RAND
Footing/Foundation/Slab 9/22/2023 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Barrier 9/22/2023 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Subgrade 9/22/2023 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 9/29/2023 Corrections Issued WILLIAM MICHALAK
METHANE-Barrier 9/29/2023 Corrections Issued WILLIAM MICHALAK
METHANE-Subgrade 9/29/2023 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 1/29/2024 Corrections Issued WILLIAM MICHALAK
METHANE-Barrier 1/29/2024 Approved WILLIAM MICHALAK
METHANE-Subgrade 1/29/2024 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 2/16/2024 Partial Approval WILLIAM MICHALAK
Footing/Foundation/Slab 2/21/2024 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 2/23/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 2/23/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 2/23/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Approval WILLIAM MICHALAK
Insulation 3/5/2024 Partial Approval WILLIAM MICHALAK
PLUMBING-Rough 3/19/2024 Partial Approval WILLIAM MICHALAK
ELECTRICAL-Rough 4/15/2024 Corrections Issued WILLIAM MICHALAK
HVAC-Rough 4/15/2024 Corrections Issued WILLIAM MICHALAK
PLUMBING-Rough 4/15/2024 Corrections Issued WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 4/15/2024 Corrections Issued WILLIAM MICHALAK
Wood Frame 4/22/2024 Partial Approval WILLIAM MICHALAK
Wood Frame 4/26/2024 Approved WILLIAM MICHALAK
Insulation 4/29/2024 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 5/10/2024 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 5/31/2024 Approved WILLIAM MICHALAK
Final 5/31/2024 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 5/31/2024 Approved WILLIAM MICHALAK
Green Building Final 5/31/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 5/31/2024 Approved WILLIAM MICHALAK
METHANE-Final 5/31/2024 Approved WILLIAM MICHALAK
METHANE-Rough 5/31/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 5/31/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 6/7/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 6/7/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 6/7/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 6/12/2024 Conditional Approval WILLIAM MICHALAK
Green Building Final 6/12/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 6/12/2024 Approved WILLIAM MICHALAK
Final 8/2/2024 Conditional Approval WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved WILLIAM MICHALAK