- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/22/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 12/30/2022 | APPLICANT |
| Plan Check Approved | 2/15/2023 | DANIEL SANJUAN |
| Issued | 2/15/2023 | APPLICANT |
| Permit Finaled | 9/12/2024 | CLAUDIO MORENO |
| CofO Issued | 9/12/2024 | CLAUDIO MORENO |
| Permit Finaled | 9/12/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 1/4/2023 | TREVOR QUAN |
| HPOZ | Cleared | 1/27/2023 | AMANDA KAINER |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2023 | Corrections Issued | GLEN RAND |
| Footing/Foundation/Slab | 9/22/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Barrier | 9/22/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Subgrade | 9/22/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 9/29/2023 | Corrections Issued | WILLIAM MICHALAK |
| METHANE-Barrier | 9/29/2023 | Corrections Issued | WILLIAM MICHALAK |
| METHANE-Subgrade | 9/29/2023 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 1/29/2024 | Corrections Issued | WILLIAM MICHALAK |
| METHANE-Barrier | 1/29/2024 | Approved | WILLIAM MICHALAK |
| METHANE-Subgrade | 1/29/2024 | Approved | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 2/21/2024 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 2/23/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Rough | 2/23/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | WILLIAM MICHALAK |
| Insulation | 3/5/2024 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 3/19/2024 | Partial Approval | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 4/15/2024 | Corrections Issued | WILLIAM MICHALAK |
| HVAC-Rough | 4/15/2024 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Rough | 4/15/2024 | Corrections Issued | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 4/15/2024 | Corrections Issued | WILLIAM MICHALAK |
| Wood Frame | 4/22/2024 | Partial Approval | WILLIAM MICHALAK |
| Wood Frame | 4/26/2024 | Approved | WILLIAM MICHALAK |
| Insulation | 4/29/2024 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 5/10/2024 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | WILLIAM MICHALAK |
| Final | 5/31/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 5/31/2024 | Approved | WILLIAM MICHALAK |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 5/31/2024 | Approved | WILLIAM MICHALAK |
| METHANE-Final | 5/31/2024 | Approved | WILLIAM MICHALAK |
| METHANE-Rough | 5/31/2024 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 6/7/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 6/7/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 6/7/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 6/12/2024 | Conditional Approval | WILLIAM MICHALAK |
| Green Building Final | 6/12/2024 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 6/12/2024 | Approved | WILLIAM MICHALAK |
| Final | 8/2/2024 | Conditional Approval | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | WILLIAM MICHALAK |