7911 N WINNETKA AVE 91306
Certificate Information: 7911 N WINNETKA AVE 91306
- Application / Permit
- 22016-10000-37859
- Plan Check / Job No.
- B22LA25259
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- TENANT IMPROVEMENTSTO BUILDING "M". IMPROVEMENT OF APPROXIMATELY 1,900 SQFT OF TENANT SPACE (E-OCCUPANCY) TO CREATE TWO ADDITIONAL CLASSROOMS WITHIN THE FOOTPRINT OF EXISITING SCHOOL BUILDING "M". REMODEL OF RESTROOMS AND ADDITIONS OF PLUMBING FIXTURES. ALL WALLLS TO BE REMOVED ON ARE NON-LOAD BEARING. NO STRUCTURAL WORK NEEDED NO CHANGE TO (E) PARKING. NO CHANGE TO STUDENT ENROLLMENT.
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/19/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | JOE VO |
| Corrections Issued | 1/9/2023 | JOE VO |
| Quality Review Completed | 1/11/2023 | KEN GILL |
| Building Plans Picked Up | 1/18/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 1/18/2023 | APPLICANT |
| Plan Check Approved | 3/20/2023 | JOE VO |
| Issued | 4/19/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/19/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2023 | DAGOVERTO GUERRERO |
| CPC | Cleared | 1/26/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 1/26/2023 | SPENCER WEJROWSKI |
| "T" removal | Cleared | 1/27/2023 | SPENCER WEJROWSKI |
| Fire Marshal Fire Life Safety | Cleared | 1/29/2023 | WILLIAM JOHNS |
| DAS Clearance | Cleared | 3/14/2023 | JOE VO |
Contact Information
| Architect | , ; Lic. No.: C36976 | , |
| Contractor | Blackwell Development Inc; Lic. No.: 1070521-B | 13229 SEVENTH PLACE YUCAIPA, CA 92399 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/22/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Wood Frame | 7/3/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/10/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 7/17/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 7/17/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 7/20/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 8/8/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 8/9/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 8/10/2023 | Approved | DEANDRE HOFFMAN |
| Final | 9/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/7/2023 | SGSOV No Gas | JEFFREY FULTON |
| Smoke Detectors | 9/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 9/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 3/6/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 5/29/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Final | 8/21/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Smoke Detectors | 8/21/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 8/21/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |