658-658 1/2 W 15TH ST 90731

Certificate Information: 658-658 1/2 W 15TH ST 90731

Application / Permit
22016-10000-37769
Plan Check / Job No.
B22LA25212
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GARAGE IN SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 2/21/2024
Issuing Office
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2022 APPLICANT
Assigned to Plan Check Engineer 12/20/2022 DANIEL YIP
Corrections Issued 12/21/2022 DANIEL YIP
Applicant returned to address corrections 6/14/2023 DANIEL YIP
Plan Check Approved 6/20/2023 JOE VO
Issued 2/21/2024 APPLICANT
CofO in Progress 12/5/2024 EUGENE CASSIDY
Permit Finaled 12/10/2024 ANSON MAGLASANG
CofO Issued 12/10/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/30/2022 AMAAN MALIK
Sewer availability Cleared 12/30/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/3/2023 AMAAN MALIK
Tenant Habitability Plan Cleared 2/7/2023 ISMAEL HERNANDEZ
Community Plan Implem. Overlay Cleared 4/10/2023 NORALI MARTINEZ
Historic Resource Verification Cleared 6/14/2023 CARTER HOWE
Redevelopment Project Area Cleared 6/14/2023 CARTER HOWE

Contact Information

Architect Khaleeli,, Bizhan; Lic. No.: C29971 4001 PACIFIC COAST HIGHWAY #108      TORRANCE, CA 90505
Contractor L J Enterprise Investments; Lic. No.: 903105-B 5701 LONG BEACH AVE STE 203      LOS ANGELES, CA 90058
Engineer Shirley,, Peter; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/26/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 3/4/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/7/2024 Approved JAMES CHAVEZ
Special/Order Compliance 3/7/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 3/20/2024 Not Ready for Inspection JAMES CHAVEZ
Wood Frame 4/15/2024 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 4/16/2024 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 4/26/2024 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 5/1/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 5/1/2024 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 5/1/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 5/3/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 5/3/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 5/6/2024 Corrections Issued EUGENE CASSIDY
HVAC-Rough 5/6/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 5/8/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 5/13/2024 Approved EUGENE CASSIDY
HVAC-Rough 5/13/2024 Approved EUGENE CASSIDY
Insulation 5/16/2024 Corrections Issued JAMES CHAVEZ
Drywall Nailing 5/20/2024 Approved JAMES CHAVEZ
Insulation 5/20/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 5/20/2024 Partial Approval JAMES CHAVEZ
Pre-Inspection 5/22/2024 Partial Inspection JAMES CHAVEZ
Interior/Exterior Lathing 5/31/2024 Partial Approval ANSON MAGLASANG
Final 12/2/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved BEN MOLSTAD
Smoke Detectors 12/2/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 12/4/2024 Approved EUGENE CASSIDY
Final 12/4/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 12/4/2024 Approved EUGENE CASSIDY
PLUMBING-Final 12/4/2024 Approved EUGENE CASSIDY