1907-1911 S MIDVALE AVE 90025
Certificate Information: 1907-1911 S MIDVALE AVE 90025
- Application / Permit
- 22016-10000-37743
- Plan Check / Job No.
- B22LA25178
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF (E) ATTACHED 2 CAR GARAGE TO JADU Per State Law
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | ZAW HAN |
| Corrections Issued | 12/20/2022 | ZAW HAN |
| Building Plans Picked Up | 12/23/2022 | APPLICANT |
| Applicant returned to address corrections | 2/2/2023 | WEIJIAN HUANG |
| Plan Check Approved | 3/13/2023 | MINA HABILI |
| Issued | 4/7/2023 | APPLICANT |
| CofO in Progress | 8/15/2024 | KIRK SANDERS |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
| CofO Issued | 9/7/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/22/2022 | ANTHONY MAINEZ |
| Address approval | Cleared | 12/30/2022 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 12/30/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 12/30/2022 | AHMED AMARRAGY |
| Grading Pre-Inspection | Cleared | 1/20/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 1/20/2023 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/30/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 6/12/2023 | Partial Approval | JESUS PINEDA |
| Deputy Drilled-In Anchors | 6/16/2023 | Conditional Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/21/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 11/29/2023 | Approved | BEN MOLSTAD |
| Gas Test | 11/29/2023 | Approved | BEN MOLSTAD |
| HVAC-Rough | 11/29/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 11/29/2023 | Approved | BEN MOLSTAD |
| Wood Frame | 11/29/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 12/1/2023 | Partial Inspection | BEN MOLSTAD |
| HVAC-Rough | 12/1/2023 | Approved | BEN MOLSTAD |
| Wood Frame | 12/1/2023 | Approved | BEN MOLSTAD |
| Insulation | 12/7/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 12/7/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 12/7/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 12/19/2023 | Approved | BEN MOLSTAD |
| Gas Test | 1/2/2024 | Approved | BEN MOLSTAD |
| Grading Pre-Inspection | 1/2/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 1/2/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 2/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Service/Power Release | 2/12/2024 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/30/2024 | Approved | ASHLEY THOMPSON |
| Final | 4/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 4/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 4/30/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Service/Power Release | 4/30/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 4/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 6/24/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 6/24/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 6/24/2024 | Approved | KIRK SANDERS |
| Final | 8/14/2024 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 8/14/2024 | Approved | KIRK SANDERS |
| Service/Power Release | 8/14/2024 | Approved | KIRK SANDERS |