5902 S 2ND AVE 90043

Certificate Information: 5902 S 2ND AVE 90043

Application / Permit
22016-10000-37671
Plan Check / Job No.
B22LA25115
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE AND (N) ADDITION INTO A BEDROOM (250 SF) TO (E) SFD
Permit Issued
Issued on 4/26/2023
Issuing Office
Metro
Current Status
Issued on 4/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2022 APPLICANT
Assigned to Plan Check Engineer 12/13/2022 FERNANDO FLORES
Corrections Issued 12/13/2022 FERNANDO FLORES
Applicant returned to address corrections 3/6/2023 VICTOR CHEN
Applicant returned to address corrections 4/3/2023 ADAM HEGAZI
Plan Check Approved 4/25/2023 MICHAEL LANZONE
Issued 4/26/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/3/2023 ABEL CASILLAS
Roof/Waste drainage to street Cleared 4/3/2023 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Schaefer,, Jeffrey; Lic. No.: C91734 3325 E 4TH ST      LONG BEACH, CA 90814

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/11/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 7/20/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/4/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/29/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 8/29/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 9/22/2023 Corrections Issued STUART CHAPMAN
Green Building Rough 9/22/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/3/2023 No Access for Inspection ANTHONY EGSON
Green Building Rough 10/3/2023 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Rough 2/16/2024 Not Ready for Inspection JOSE MACIAS
ELECTRICAL-Rough 2/28/2024 Conditional Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Approved JOSE MACIAS
Green Building Rough 3/12/2024 Not Ready for Inspection JOSE MACIAS
ELECTRICAL-Rough 5/23/2024 Not Ready for Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Approved JOSE MACIAS
Green Building Rough 5/23/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 5/23/2024 Not Ready for Inspection JOSE MACIAS
Insulation 5/31/2024 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 5/31/2024 Partial Approval JOSH MEISTER
Drywall Nailing 7/16/2024 Approved JOSE MACIAS
Green Building Rough 7/16/2024 Approved JOSE MACIAS