5902 S 2ND AVE 90043
Certificate Information: 5902 S 2ND AVE 90043
- Application / Permit
- 22016-10000-37671
- Plan Check / Job No.
- B22LA25115
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE AND (N) ADDITION INTO A BEDROOM (250 SF) TO (E) SFD
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/26/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2022 | FERNANDO FLORES |
| Corrections Issued | 12/13/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 3/6/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 4/3/2023 | ADAM HEGAZI |
| Plan Check Approved | 4/25/2023 | MICHAEL LANZONE |
| Issued | 4/26/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 4/3/2023 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schaefer,, Jeffrey; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/20/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/4/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/29/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 8/29/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/3/2023 | No Access for Inspection | ANTHONY EGSON |
| Green Building Rough | 10/3/2023 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/16/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 2/28/2024 | Conditional Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 3/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 5/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 5/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Insulation | 5/31/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 5/31/2024 | Partial Approval | JOSH MEISTER |
| Drywall Nailing | 7/16/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 7/16/2024 | Approved | JOSE MACIAS |