10722-10724 W STAGG ST 91352

Certificate Information: 10722-10724 W STAGG ST 91352

Application / Permit
22016-10000-37579
Plan Check / Job No.
B22LA25067
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER STATE LAW.
Permit Issued
Issued on 5/15/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2022 APPLICANT
Assigned to Plan Check Engineer 12/12/2022 LAWRENCE QUIRANTE
Corrections Issued 12/12/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/11/2023 VICTOR CHEN
Plan Check Approved 1/27/2023 GEORGE ALVAREZ
Issued 5/15/2023 APPLICANT
CofO in Progress 10/19/2023 CHRISTOPHER ROJAS
Permit Finaled 11/15/2023 RUBEN SALAS
Permit Finaled 11/15/2023 RUBEN SALAS
CofO Issued 11/15/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/13/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/13/2022 AMAAN MALIK
Sewer availability Cleared 12/13/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/8/2023 Approved MATTHEW NELSON
PLUMBING-Rough 6/30/2023 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 7/10/2023 Approved MATTHEW NELSON
PLUMBING-Rough 7/10/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/19/2023 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 7/19/2023 Approved MATTHEW NELSON
Wood Frame 7/19/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/24/2023 Approved MATTHEW NELSON
Insulation 7/28/2023 Approved WILLIAM WREN
Drywall Nailing 8/1/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 8/4/2023 Approved MATTHEW NELSON
Shower Pan 8/4/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/13/2023 Corrections Issued CHRISTOPHER ROJAS
Final 10/13/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/13/2023 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/13/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/18/2023 Approved CHRISTOPHER ROJAS
Final 10/18/2023 OK to Issue CofO CHRISTOPHER ROJAS
Wood Frame 10/18/2023 Approved CHRISTOPHER ROJAS
Service/Power Release 11/15/2023 Approved JUAN VALENZUELA