2425 S BARRINGTON AVE 90064
Certificate Information: 2425 S BARRINGTON AVE 90064
- Application / Permit
- 22016-10000-37493
- Plan Check / Job No.
- B22LA24998
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Soft story seismic reinforcement at building parking garage using (1) special cantilevered column with grade beam.
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- CofC Issued on 8/16/2023
Permit Application Status History
| Submitted | 12/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | VARAND SARKISIAN |
| Corrections Issued | 1/9/2023 | VARAND SARKISIAN |
| Quality Review Completed | 1/17/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/6/2023 | VARAND SARKISIAN |
| Plan Check Approved | 2/16/2023 | VARAND SARKISIAN |
| Issued | 3/20/2023 | APPLICANT |
| OK for CofC | 8/11/2023 | MICHAEL PETRUSKO |
| CofC Issued | 8/16/2023 | DAVID TSAU |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/7/2023 | KYLE WINSTON |
| Tenant Habitability Plan | Cleared | 3/20/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | One Structural Inc; Lic. No.: 1003868-B | , |
| Contractor | Retrofit 1; Lic. No.: 1003868-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2023 | Not Ready for Inspection | ALAN NOVAK |
| Deputy Steel/Welding | 4/28/2023 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 5/10/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Structural Steel Frame | 5/10/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Wood Frame | 5/10/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 5/11/2023 | Approved | ALAN NOVAK |
| Structural Steel Frame | 5/11/2023 | Approved | ALAN NOVAK |
| Wood Frame | 5/11/2023 | Approved | ALAN NOVAK |
| Drywall Nailing | 6/2/2023 | Approved | ALAN NOVAK |
| Final | 7/14/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 7/14/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 8/10/2023 | Conditional Approval | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 8/10/2023 | Approved | MICHAEL PETRUSKO |
| Final | 8/11/2023 | OK for CofC | MICHAEL PETRUSKO |