4037 S TIVOLI AVE 90066

Certificate Information: 4037 S TIVOLI AVE 90066

Application / Permit
22016-10000-37397
Plan Check / Job No.
B22LA24979
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (376 SQ FT) PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 1/25/2023
Issuing Office
Current Status
CofO Issued on 3/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 JEROME MAGAT PALMA
Corrections Issued 12/17/2022 JEROME MAGAT PALMA
Plan Check Approved 1/24/2023 JEROME MAGAT PALMA
Issued 1/25/2023 APPLICANT
CofO in Progress 12/8/2023 RICHARD STEINBACH
Permit Finaled 3/19/2024 DANIEL ORRANTE
CofO Issued 3/19/2024 DANIEL ORRANTE
Permit Finaled 3/19/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/22/2022 DINAH GARIN
Sewer availability Cleared 12/22/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/27/2022 DINAH GARIN
Specific Plan Cleared 1/3/2023 FREDDY GARCIA

Contact Information

Contractor Green Works Construction & Design Inc; Lic. No.: 936962-B       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/1/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/13/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 6/13/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 6/22/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/22/2023 Corrections Issued JESUS RODRIGUEZ
Insulation 6/26/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Corrections Issued JESUS RODRIGUEZ
Insulation 7/7/2023 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 7/7/2023 Corrections Issued JESUS RODRIGUEZ
Shower Pan 7/7/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 7/17/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 7/17/2023 Partial Approval HERBERT GIRON
Drywall Nailing 7/24/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 8/1/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 8/1/2023 Approved JESUS RODRIGUEZ
Green Building Rough 8/1/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 8/1/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/1/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/1/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Not Ready HERBERT GIRON
ELECTRICAL-Final 11/20/2023 Approved JESUS RODRIGUEZ
Final 11/20/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/20/2023 Approved JESUS RODRIGUEZ
HVAC-Final 11/20/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/20/2023 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/20/2023 Approved JESUS RODRIGUEZ
Final 11/29/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 11/29/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/29/2023 Approved JESUS RODRIGUEZ