1743 S VIRGINIA ROAD 90019

Certificate Information: 1743 S VIRGINIA ROAD 90019

Application / Permit
22016-10000-37343
Plan Check / Job No.
B22LA24945
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ADU PER GCS 65852.2(e)(1)(A). No additional floor Area proposed.
Permit Issued
Issued on 1/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 ZAW HAN
Corrections Issued 12/20/2022 ZAW HAN
Building Plans Picked Up 1/3/2023 APPLICANT
Plan Check Approved 1/26/2023 WEIJIAN HUANG
Issued 1/31/2023 APPLICANT
CofO in Progress 8/21/2023 CALEB MEISTER
CofO Issued 8/23/2023 DEROLD HAUFF
Permit Finaled 8/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 1/6/2023 CELINA MORENO
Sewer availability Cleared 1/6/2023 CELINA MORENO
HPOZ Cleared 1/13/2023 AMANDA KAINER
ZI Cleared 1/13/2023 AMANDA KAINER
Eng Process Fee Ord 176,300 Cleared 1/18/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/22/2023 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 3/15/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 3/15/2023 Approved CALEB MEISTER
Footing/Foundation/Slab 3/15/2023 Approved CALEB MEISTER
Green Building Rough 3/15/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Rough 3/15/2023 Not Ready for Inspection CALEB MEISTER
Wood Frame 3/15/2023 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 3/23/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 3/23/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 3/23/2023 Not Ready for Inspection CALEB MEISTER
Deputy Drilled-In Anchors 3/24/2023 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 4/18/2023 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/18/2023 Approved STUART CHAPMAN
Green Building Rough 4/18/2023 Not Ready for Inspection STUART CHAPMAN
Grounding or Bonding 4/18/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 4/18/2023 Approved STUART CHAPMAN
METHANE-Rough 4/18/2023 Approved STUART CHAPMAN
Shower Pan 4/18/2023 Approved STUART CHAPMAN
Insulation 4/25/2023 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 4/25/2023 Corrections Issued RICHARD DOCKUS
Drywall Nailing 5/3/2023 Not Ready for Inspection CALEB MEISTER
Insulation 5/3/2023 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 5/3/2023 Approved CALEB MEISTER
Drywall Nailing 5/11/2023 Corrections Issued CALEB MEISTER
Drywall Nailing 5/25/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 7/12/2023 Approved CALEB MEISTER
ELECTRICAL-Final 7/12/2023 Corrections Issued CALEB MEISTER
Green Building Final 7/12/2023 Approved CALEB MEISTER
Green Building Rough 7/12/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 7/12/2023 Approved CALEB MEISTER
Final 7/28/2023 Conditional Approval CALEB MEISTER
Final 8/21/2023 OK to Issue CofO CALEB MEISTER