4422 W MELBOURNE AVE 1-5 90027

Certificate Information: 4422 W MELBOURNE AVE 1-5 90027

Application / Permit
22016-10000-37212
Plan Check / Job No.
B22LA24878
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EX. BASEMENT SPACE INTO ACCESSORY DWELLING UNIT ( UNIT #5 ) PER CA GOV STATE CODE FOR EX. 4-UNIT APARTMENT. WORK PER ENGINEER.
Permit Issued
Issued on 1/31/2023
Issuing Office
Current Status
CofO Issued on 6/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 ROSENDO MEDINA
Corrections Issued 12/21/2022 ROSENDO MEDINA
Applicant returned to address corrections 1/13/2023 ROSENDO MEDINA
Plan Check Approved 1/30/2023 ROSENDO MEDINA
Issued 1/31/2023 APPLICANT
CofO in Progress 6/14/2024 RAFAEL CORTES
Permit Finaled 6/18/2024 ERNESTO CORRAL
CofO Issued 6/18/2024 ERNESTO CORRAL

Permit Application Clearance Information

Sewer availability Cleared 1/13/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/17/2023 STEVE MELGAR
ZA Case Cleared 1/18/2023 ANACANY HURTADO
ZA Case Cleared 1/18/2023 ANACANY HURTADO
Address approval Cleared 1/24/2023 STEVE MELGAR
Grading Pre-Inspection Cleared 1/30/2023 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2023 Conditional Approval TIMOTHY POWELL
Wood Frame 10/6/2023 Partial Approval RICARDO ROBLES
Insulation 10/11/2023 No Access for Inspection VAHE KELEDJIAN
Insulation 10/11/2023 Partial Approval JACOB MYERS
Deputy Wood Construction 10/17/2023 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 11/2/2023 Corrections Issued GREGORY POMISH
Green Building Rough 11/27/2023 Approved RONALD JIMENEZ
Wood Frame 11/27/2023 Approved RONALD JIMENEZ
Drywall Nailing 12/1/2023 Approved RONALD JIMENEZ
Interior/Exterior Lathing 12/14/2023 Partial Approval RONALD JIMENEZ
Final 5/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 5/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 5/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 5/23/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Final 5/23/2024 Not Ready for Inspection RAFAEL CORTES
Smoke Detectors 5/23/2024 Approved RAFAEL CORTES
Final 6/5/2024 Not Ready for Inspection RAFAEL CORTES
Green Building Final 6/5/2024 Not Ready for Inspection RAFAEL CORTES
Final 6/14/2024 OK to Issue CofO RAFAEL CORTES
Green Building Final 6/14/2024 Approved RAFAEL CORTES