842 W 81ST ST 1-3 90044
Certificate Information: 842 W 81ST ST 1-3 90044
- Application / Permit
- 22016-10000-37144
- Plan Check / Job No.
- B22LA24827
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT SFD TO DUPLEX IN SECOND FLOOR CONVERT REC ROOM (288 SQ FT) + & STORAGE(207 SQ FT) TO 495 SQ FT OF ADU PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | VARAND SARKISIAN |
| Corrections Issued | 12/20/2022 | VARAND SARKISIAN |
| Quality Review Completed | 12/22/2022 | HANS SANTIAGO |
| Building Plans Picked Up | 3/15/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 9/27/2023 | APPLICANT |
| Plan Check Approved | 5/9/2024 | VARAND SARKISIAN |
| Issued | 5/13/2024 | APPLICANT |
| CofO in Progress | 7/9/2025 | JOHN QUINTANILLA |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| CofO Issued | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2023 | STEVE MELGAR |
| Hold | Cleared | 5/4/2023 | MARIA VENDIVIL |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 5/24/2023 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 6/7/2023 | GILBERT URREA |
| "Q" conditions | Cleared | 6/8/2023 | LOUIS ORTEGA |
| DAS Clearance | Cleared | 4/23/2024 | ANDREW SANTIAGO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/4/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/4/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 6/4/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Insulation | 6/4/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 6/4/2024 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/17/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/17/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/17/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 7/17/2024 | Approved | MICHAEL LEWIS |
| Insulation | 7/17/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/17/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/9/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/9/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| Final | 3/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 3/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Final | 3/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Final | 3/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 3/13/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 7/1/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 7/1/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 7/1/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 7/1/2025 | Corrections Issued | BARRY HACHE |
| Final | 7/8/2025 | OK to Issue CofO | JOHN QUINTANILLA |
| Green Building Final | 7/8/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 7/8/2025 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 7/8/2025 | Approved | JOHN QUINTANILLA |