5340-5342 N MELGRE AVE 91367
Certificate Information: 5340-5342 N MELGRE AVE 91367
- Application / Permit
- 22016-10000-36988
- Plan Check / Job No.
- B22LA24688
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert attached garage and (270 SF) portion of (E) 1-story SFD into Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP.
- Permit Issued
- Issued on 7/14/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | VICTOR CHEN |
| Corrections Issued | 12/10/2022 | VICTOR CHEN |
| Building Plans Picked Up | 3/8/2023 | APPLICANT |
| Plan Check Approved | 7/11/2023 | MICHAEL LANZONE |
| Issued | 7/14/2023 | APPLICANT |
| CofO in Progress | 12/4/2023 | TROY SANDERS |
| Permit Finaled | 12/4/2023 | JOHN JANSON |
| CofO Issued | 12/4/2023 | JOHN JANSON |
| Permit Finaled | 12/4/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/5/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/5/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/21/2023 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 7/24/2023 | Not Ready for Inspection | TROY SANDERS |
| Drywall Nailing | 7/24/2023 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 7/24/2023 | Approved | TROY SANDERS |
| Green Building Final | 7/24/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 7/24/2023 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 7/24/2023 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 8/28/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 8/28/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/28/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 9/12/2023 | Approved | TROY SANDERS |
| Green Building Rough | 9/12/2023 | Approved | TROY SANDERS |
| Insulation | 9/12/2023 | Approved | TROY SANDERS |
| Shower Pan | 9/12/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 12/1/2023 | Approved | TROY SANDERS |
| Final | 12/1/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 12/1/2023 | Approved | TROY SANDERS |
| HVAC-Final | 12/1/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 12/1/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 12/1/2023 | Approved | TROY SANDERS |