369 N VAN NESS AVE 90004
Certificate Information: 369 N VAN NESS AVE 90004
- Application / Permit
- 22016-10000-36986
- Plan Check / Job No.
- B22LA24683
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) Garage/storage to Accesry Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/1/2023
- Issuing Office
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2022 | EDWIN ESPIN |
| Corrections Issued | 12/14/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 1/12/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 3/14/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 3/16/2023 | EDWIN ESPIN |
| Plan Check Approved | 4/4/2023 | EDWIN ESPIN |
| Plan Check Approved | 8/31/2023 | EDWIN ESPIN |
| Issued | 9/1/2023 | APPLICANT |
| CofO in Progress | 11/17/2023 | JEFFREY MEAD |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 12/15/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 3/8/2023 | GILBERT URREA |
Contact Information
| Architect | Grumbine,, Anthony; Lic. No.: C36146 | 35 W HALEY ST SANTA BARBARA , CA 93101 |
| Contractor | Dave C Inc; Lic. No.: 920202-B | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/6/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 9/6/2023 | Approved | JEFFREY MEAD |
| Insulation | 9/6/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/6/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/8/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | JEFFREY MEAD |
| Final | 10/12/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 10/12/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 10/12/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 10/12/2023 | Approved | JEFFREY MEAD |
| Final | 11/16/2023 | OK to Issue CofO | JEFFREY MEAD |