369 N VAN NESS AVE 90004

Certificate Information: 369 N VAN NESS AVE 90004

Application / Permit
22016-10000-36986
Plan Check / Job No.
B22LA24683
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) Garage/storage to Accesry Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/1/2023
Issuing Office
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2022 APPLICANT
Assigned to Plan Check Engineer 12/14/2022 EDWIN ESPIN
Corrections Issued 12/14/2022 EDWIN ESPIN
Applicant returned to address corrections 1/12/2023 ALFREDO JARA
Applicant returned to address corrections 3/14/2023 EDWIN ESPIN
Applicant returned to address corrections 3/16/2023 EDWIN ESPIN
Plan Check Approved 4/4/2023 EDWIN ESPIN
Plan Check Approved 8/31/2023 EDWIN ESPIN
Issued 9/1/2023 APPLICANT
CofO in Progress 11/17/2023 JEFFREY MEAD
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/15/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/15/2022 TREVOR QUAN
Sewer availability Cleared 12/15/2022 TREVOR QUAN
Hydrant and Access approval Cleared 3/8/2023 GILBERT URREA

Contact Information

Architect Grumbine,, Anthony; Lic. No.: C36146 35 W HALEY ST   SANTA BARBARA    , CA 93101
Contractor Dave C Inc; Lic. No.: 920202-B       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/6/2023 Approved JEFFREY MEAD
HVAC-Rough 9/6/2023 Approved JEFFREY MEAD
Insulation 9/6/2023 Approved JEFFREY MEAD
PLUMBING-Rough 9/6/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 9/8/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/12/2023 Approved JEFFREY MEAD
Final 10/12/2023 Corrections Issued JEFFREY MEAD
Green Building Final 10/12/2023 Approved JEFFREY MEAD
Green Building Rough 10/12/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 10/12/2023 Approved JEFFREY MEAD
Final 11/16/2023 OK to Issue CofO JEFFREY MEAD