15029 W VALLEYHEART DR 91403

Certificate Information: 15029 W VALLEYHEART DR 91403

Application / Permit
22016-10000-36929
Plan Check / Job No.
B22LA24636
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. Interior/Exterior alteration to (E) 2 story SFD
Permit Issued
Issued on 1/10/2023
Issuing Office
Current Status
Permit Finaled on 9/15/2023

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/13/2022 PRANITA SHAH
Corrections Issued 12/14/2022 PRANITA SHAH
Applicant returned to address corrections 12/27/2022 PRANITA SHAH
Plan Check Approved 1/6/2023 KEVIN MORALES
Issued 1/10/2023 APPLICANT
Permit Finaled 9/14/2023 THOMAS FINNILA

Permit Application Clearance Information

ZI Cleared 12/19/2022 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 12/21/2022 FERNANDO GIL
Roof/Waste drainage to street Cleared 12/21/2022 FERNANDO GIL
Sewer availability Cleared 12/21/2022 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 3/23/2023 Not Ready for Inspection THOMAS FINNILA
Reinforced Masonry Frame 3/23/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 3/23/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 3/24/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 3/24/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 3/30/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 3/30/2023 Approved JOHN COLEMAN
Wood Frame 4/13/2023 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 8/18/2023 Approved THOMAS FINNILA
Final 8/18/2023 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 8/18/2023 Approved THOMAS FINNILA
Final 9/5/2023 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Final 9/5/2023 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 9/5/2023 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Not Ready THOMAS FINNILA
Final 9/14/2023 Permit Finaled THOMAS FINNILA
MERV13>=Final 9/14/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/14/2023 SGSOV Approved THOMAS FINNILA
Smoke Detectors 9/14/2023 Approved THOMAS FINNILA