735 S APPELBY ST 90291
Certificate Information: 735 S APPELBY ST 90291
- Application / Permit
- 22016-10000-36478
- Plan Check / Job No.
- B22LA23189
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Conversion of an (E) detached into an ADU per GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | HELEN NGUYEN |
| Corrections Issued | 12/6/2022 | HELEN NGUYEN |
| Quality Review Completed | 12/20/2022 | MICHAEL PEREZ |
| Applicant returned to address corrections | 1/26/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/2/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/28/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/14/2023 | HELEN NGUYEN |
| Plan Check Approved | 3/23/2023 | HELEN NGUYEN |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 2/28/2024 | HERBERT GIRON |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| CofO Issued | 2/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2023 | DINAH GARIN |
| Sewer availability | Cleared | 1/6/2023 | DINAH GARIN |
| Specific Plan | Cleared | 1/25/2023 | ALESSANDRO MERCURI |
| Low Impact Development | Cleared | 2/9/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/17/2023 | DINAH GARIN |
| Construction within easement | Cleared | 3/21/2023 | TINA MIRANDA |
Contact Information
| Architect | Liu,, Siyuan; Lic. No.: C39404 | 1701 NAVARRO AVE PASADENA, CA 91103 |
| Contractor | California Realty & Investment Group Inc; Lic. No.: 929543-B | , |
| Engineer | Zhao,, Zhisong; Lic. No.: S6814 | 2376 CHALYBE TRAIL HOOVER, AL 35226 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/14/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/14/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/19/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 5/19/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/19/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 5/19/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/24/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/25/2023 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 5/25/2023 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 5/25/2023 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 5/31/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 6/5/2023 | Approved | EVAN COOPER |
| Green Building Rough | 6/5/2023 | Approved | EVAN COOPER |
| Insulation | 6/7/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 6/21/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/13/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/13/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 11/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 11/17/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 11/17/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 11/22/2023 | Approved | HERBERT GIRON |
| Final | 11/22/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/22/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 11/22/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/22/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 11/22/2023 | Approved | HERBERT GIRON |
| Final | 12/11/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 12/11/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 12/11/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Approved | HERBERT GIRON |
| Final | 12/13/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 12/13/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 1/5/2024 | Approved | HERBERT GIRON |
| Final | 2/27/2024 | OK to Issue CofO | HERBERT GIRON |