611 W LACONIA BLVD 90044

Certificate Information: 611 W LACONIA BLVD 90044

Application / Permit
22016-10000-36285
Plan Check / Job No.
B22LA24229
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: REMODEL: RECONFIGURATION OF BEDROOM LAYOUTS, (2) BATHROOMS REMODEL, KITCHEN REMODEL, ENLARGING DOORWAYS FOR EGRESS, REPLACING AND ADDING (N) WINDOWS FOR EGRESS, (N) CONC. RAMP ON THE WEST, EAST AND SOUTH SIDE OF THE HOUSE FOR ACCESSIBILITY. SEE COMMENTS.
Permit Issued
Issued on 8/17/2023
Issuing Office
Current Status
Permit Finaled on 2/14/2024

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/7/2022 JASON JANGADA
Corrections Issued 12/9/2022 AMY GUEVARRA
Applicant returned to address corrections 1/28/2023 JASON JANGADA
Applicant returned to address corrections 2/10/2023 JASON JANGADA
Applicant returned to address corrections 2/22/2023 JASON JANGADA
Applicant returned to address corrections 3/30/2023 JASON JANGADA
Plan Check Approved 8/11/2023 JASON JANGADA
Issued 8/17/2023 APPLICANT
Permit Finaled 2/13/2024 JAMES CHAVEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/22/2022 ANA SORIANO
Roof/Waste drainage to street Cleared 1/4/2023 ANA SORIANO
Sewer availability Cleared 1/9/2023 ANA SORIANO

Contact Information

Contractor Xcel Builders Inc; Lic. No.: 778621-B       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/7/2023 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Partial Approval JOHN KLARIN
Gas Test 10/5/2023 Approved JOHN KLARIN
PLUMBING-Rough 10/5/2023 Approved JOHN KLARIN
Sewer 10/5/2023 Approved JOHN KLARIN
Insulation 10/11/2023 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval JAMES CHAVEZ
Wood Frame 10/12/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 10/18/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 10/18/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 10/18/2023 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 10/18/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 10/18/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 10/23/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 10/23/2023 Approved JAMES CHAVEZ
HVAC-Rough 10/23/2023 Approved JAMES CHAVEZ
MERV13>=Rough 10/23/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 10/23/2023 Approved JAMES CHAVEZ
Wood Frame 10/23/2023 Not Ready for Inspection JAMES CHAVEZ
Interior/Exterior Lathing 11/16/2023 Approved JOHN KLARIN
Wood Frame 11/16/2023 Approved JOHN KLARIN
Insulation 11/28/2023 Approved JAMES CHAVEZ
Shower Pan 11/28/2023 Approved JAMES CHAVEZ
Drywall Nailing 12/6/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 12/6/2023 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 2/1/2024 Approved JAMES CHAVEZ
ELECTRICAL-Final 2/1/2024 Not Ready for Inspection JAMES CHAVEZ
Final 2/1/2024 Corrections Issued JAMES CHAVEZ
HVAC-Final 2/1/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Final 2/1/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Final 2/1/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 2/1/2024 Approved JAMES CHAVEZ
ELECTRICAL-Final 2/13/2024 Approved JAMES CHAVEZ
Final 2/13/2024 Permit Finaled JAMES CHAVEZ
HVAC-Final 2/13/2024 Approved JAMES CHAVEZ
MERV13>=Final 2/13/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Approved JAMES CHAVEZ