1031-1031 1/2 E CRUCES ST 90744

Certificate Information: 1031-1031 1/2 E CRUCES ST 90744

Application / Permit
22016-10000-36269
Plan Check / Job No.
B22LA24214
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert rear portion of existing 1-story single family dwelling into ADU ,remodel existing SFD and convert attached garage to JADU per State Law CA Govt. Code 65852.2(e)(1)(A), per WFPP "COMPLY WITH DEPARTMENT ORDER effective date 10/11/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 12/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 12/5/2022 VICTOR CHEN
Corrections Issued 12/5/2022 VICTOR CHEN
Building Plans Picked Up 12/7/2022 APPLICANT
Applicant returned to address corrections 12/21/2022 MINA HABILI
Plan Check Approved 12/30/2022 LUKE GONZALES
Plan Check Approved 12/30/2022 LUKE GONZALES
Issued 12/30/2022 APPLICANT
CofO in Progress 8/17/2023 BRIAN CHRISTIAN
Permit Finaled 9/12/2023 BRUCE TODD
CofO Issued 9/12/2023 BRUCE TODD
Permit Finaled 9/12/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 12/16/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/16/2022 JEANIE LAM
Sewer availability Cleared 12/16/2022 JEANIE LAM
Miscellaneous Cleared 12/30/2022 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/6/2023 Approved BRIAN CHRISTIAN
Excavation/Setback/Form/Re-Bar 3/13/2023 Approved BRIAN CHRISTIAN
Footing/Foundation/Slab 3/13/2023 Approved BRIAN CHRISTIAN
Sewer 3/13/2023 Approved BRIAN CHRISTIAN
Underground Mechanical 3/13/2023 Partial Approval BRIAN CHRISTIAN
Gas Test 4/3/2023 Partial Approval BRIAN CHRISTIAN
Insulation 4/3/2023 Partial Approval BRIAN CHRISTIAN
METHANE-Rough 4/3/2023 Approved BRIAN CHRISTIAN
Underground Mechanical 4/3/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 4/24/2023 Corrections Issued BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Approved BRIAN CHRISTIAN
Gas Test 4/24/2023 Approved BRIAN CHRISTIAN
HVAC-Rough 4/24/2023 Corrections Issued BRIAN CHRISTIAN
PLUMBING-Rough 4/24/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 4/27/2023 Approved BRIAN CHRISTIAN
Green Building Rough 4/27/2023 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/27/2023 Partial Approval BRIAN CHRISTIAN
HVAC-Rough 5/1/2023 Partial Approval BRIAN CHRISTIAN
Insulation 5/1/2023 Approved BRIAN CHRISTIAN
Shower Pan 5/1/2023 Approved BRIAN CHRISTIAN
Drywall Nailing 5/11/2023 Partial Approval BRIAN CHRISTIAN
Green Building Rough 5/11/2023 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/31/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 7/6/2023 Approved BRIAN CHRISTIAN
HVAC-Rough 7/6/2023 Corrections Issued BRIAN CHRISTIAN
PLUMBING-Rough 7/6/2023 Approved BRIAN CHRISTIAN
Drywall Nailing 7/17/2023 Approved BRIAN CHRISTIAN
HVAC-Rough 7/17/2023 Not Ready for Inspection BRIAN CHRISTIAN
BUILDING-Rough-Frame 8/10/2023 Approved BRIAN CHRISTIAN
Final 8/10/2023 Not Ready for Inspection BRIAN CHRISTIAN
SGSOV-Seismic Gas S/O Valve 8/10/2023 SGSOV Approved BRIAN CHRISTIAN
Smoke Detectors 8/10/2023 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 8/14/2023 Approved BRIAN CHRISTIAN
PLUMBING-Final 8/14/2023 Approved BRIAN CHRISTIAN
Final 8/17/2023 OK to Issue CofO BRIAN CHRISTIAN
HVAC-Final 8/17/2023 Approved BRIAN CHRISTIAN