300 WORLD WAY 352 90045
Certificate Information: 300 WORLD WAY 352 90045
- Application / Permit
- 22016-10000-36205
- Plan Check / Job No.
- B22LA24179
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX**Project Under Construction** First time tenant improvement for a food and beverage space, 991 SF.
- Permit Issued
- Issued on 1/3/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/28/2024
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | EDUARDO RODRIGUEZ |
| Corrections Issued | 12/28/2022 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 12/28/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 6/7/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 10/24/2023 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 10/29/2023 | EDUARDO RODRIGUEZ |
| Issued | 1/3/2024 | APPLICANT |
| Permit Finaled | 8/28/2024 | ALAN NOVAK |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 4/10/2023 | EDUARDO RODRIGUEZ |
| Project Permit | Cleared | 4/21/2023 | EDUARDO RODRIGUEZ |
| Airport buildings | Cleared | 5/3/2023 | ANDREW KO |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/27/2023 | ANTHONY MAINEZ |
| DAS Clearance | Cleared | 9/28/2023 | Lily Teng |
| Green Code | Cleared | 9/28/2023 | AARON COSTA |
| Food establishment approval | Cleared | 10/24/2023 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 10/25/2023 | KENNETH BROWNE |
Contact Information
| Architect | Garg,, Satyakam; Lic. No.: NA11579 | , |
| Contractor | Premier Interior Development Inc; Lic. No.: 630171-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/19/2024 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 4/22/2024 | Approved | ALAN NOVAK |
| Drywall Nailing | 4/23/2024 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 4/25/2024 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 5/1/2024 | Corrections Issued | ALAN NOVAK |
| Light Gage Steel Frame | 5/9/2024 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/3/2024 | Not Ready for Inspection | ALAN NOVAK |
| Light Gage Steel Frame | 6/5/2024 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 6/27/2024 | Not Ready for Inspection | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/9/2024 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 7/23/2024 | Approved | ALAN NOVAK |
| T-Bar Ceiling | 7/23/2024 | Approved | ALAN NOVAK |
| Final | 8/23/2024 | Not Ready for Inspection | ALAN NOVAK |
| Green Building Final | 8/23/2024 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 8/23/2024 | Approved | ALAN NOVAK |