2250 S MAPLE AVE 90011
Certificate Information: 2250 S MAPLE AVE 90011
- Application / Permit
- 22016-10000-36194
- Plan Check / Job No.
- B22LA24171
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- CONVERT (E) SHOWER STALLS TO TOILET STALLS
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/5/2023
Permit Application Status History
| Submitted | 11/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2022 | ADAM HEGAZI |
| Corrections Issued | 12/7/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 12/22/2022 | APPLICANT |
| Plan Check Approved | 12/23/2022 | RICARDO RAMIREZ |
| Issued | 12/23/2022 | APPLICANT |
| Permit Finaled | 5/5/2023 | MARTIN TAVITIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-B | 940 S WESTERN AVE #B LOS ANGELES, CA 90006 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 5/5/2023 | Permit Finaled | MARTIN TAVITIAN |
| Smoke Detectors | 5/5/2023 | Approved | MARTIN TAVITIAN |