12310 W VENICE BLVD 90066
Certificate Information: 12310 W VENICE BLVD 90066
- Application / Permit
- 22016-10000-36170
- Plan Check / Job No.
- B22LA24134
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan INTERIOR RENOVATION OF EXISTING COMMERCIAL ONE-STORY BUILDING, Upgrade of Accessibility and Restriping of Parking Area.
- Permit Issued
- Issued on 5/10/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/3/2026
Permit Application Status History
| Submitted | 11/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 12/11/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/13/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/15/2023 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/13/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/15/2023 | ARSALAN SHABESTARI |
| Issued | 5/10/2024 | APPLICANT |
| Permit Finaled | 4/3/2026 | FARHAD DADBIN |
Permit Application Clearance Information
| Green Code | Cleared | 12/9/2022 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 2/28/2023 | Lawrence Quirante |
Contact Information
| Contractor | Capasso Construction Inc; Lic. No.: 333398-B | 548 W 20TH STREET UPLAND, CA 91784 |
| Engineer | Howe,, Carl William; Lic. No.: NA44773 | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 7/24/2024 | Partial Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 8/2/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 8/7/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 8/16/2024 | Approved | AMANUEL BERHE |
| Wood Frame | 11/7/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 12/19/2024 | Conditional Approval | FARHAD DADBIN |
| Wood Frame | 1/9/2025 | Conditional Approval | FARHAD DADBIN |
| Drywall Nailing | 3/18/2025 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 7/24/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Interior/Exterior Lathing | 7/29/2025 | Approved | FARHAD DADBIN |
| Final | 3/9/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 3/9/2026 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 3/9/2026 | Approved | FARHAD DADBIN |
| Final | 4/3/2026 | Permit Finaled | FARHAD DADBIN |
| Green Building Final | 4/3/2026 | Approved | FARHAD DADBIN |