6217 E HILLANDALE DR 90042
Certificate Information: 6217 E HILLANDALE DR 90042
- Application / Permit
- 22016-10000-35815
- Plan Check / Job No.
- B22LA23923
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of attached Garage TO LIVING ROOM AND BEDROOM NEW GARAGE ADDITION TO SFD.
- Permit Issued
- Issued on 7/23/2024
- Issuing Office
- Current Status
- Issued on 7/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2022 | JOE VO |
| Corrections Issued | 12/24/2022 | JOE VO |
| Quality Review Completed | 12/27/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/24/2023 | JOE VO |
| Plan Check Approved | 7/11/2023 | JOE VO |
| Issued | 7/23/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/17/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/17/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/17/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/17/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/17/2023 | TREVOR QUAN |
| Permit | Cleared | 3/17/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 3/17/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 5/18/2023 | JOHN CONNEALLY |
| Grading Pre-Inspection | Cleared | 7/11/2023 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Reinforced Masonry Frame | 11/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Masonry Wall/Backfill | 12/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/18/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Masonry Wall/Backfill | 12/30/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 1/2/2025 | Partial Approval | CRAIG DAVIS |
| Masonry Wall/Backfill | 1/14/2025 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/16/2025 | Approved | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 1/31/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/22/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 5/22/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 8/29/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 8/29/2025 | Approved | DAVID WILLIAMS |
| Insulation | 9/16/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 9/16/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 9/23/2025 | Not Ready for Inspection | REGINA MENDEZ |
| Drywall Nailing | 9/25/2025 | Approved | REGINA MENDEZ |
| Final | 12/19/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 12/19/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 12/19/2025 | Approved | JEFFREY MEAD |