990 E SUNSET AVE 90291
Certificate Information: 990 E SUNSET AVE 90291
- Application / Permit
- 22016-10000-35810
- Plan Check / Job No.
- B22LA23919
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. EXTERIOR AND INTERIOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/5/2024
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2022 | DANIEL YIP |
| Corrections Issued | 12/4/2022 | DANIEL YIP |
| Applicant returned to address corrections | 2/3/2023 | MADISON ODELL |
| Plan Check Approved | 3/6/2023 | JAHANSHAH POURHASSAN |
| No Progress | 3/6/2023 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 3/6/2023 | JAHANSHAH POURHASSAN |
| Issued | 3/8/2023 | APPLICANT |
| Permit Finaled | 4/4/2024 | HERBERT GIRON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Duvivier,, Isabelle L; Lic. No.: C26807 | 350 WESTMINSTER AVENUE VENICE, CA 90291 |
| Contractor | Owner-Builder | , |
| Engineer | Chiang,, Eric K; Lic. No.: L6671 | 301 W OAKMONT DR MONTEBELLO, CA 90640 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/18/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 6/30/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 6/30/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 7/6/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 7/6/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 7/6/2023 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 7/7/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/7/2023 | Approved | EVAN COOPER |
| Insulation | 7/13/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 7/19/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/5/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/28/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/28/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/28/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/13/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 12/13/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 12/13/2023 | Approved | HERBERT GIRON |
| Final | 4/4/2024 | Permit Finaled | HERBERT GIRON |
| PLUMBING-Final | 4/4/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 4/4/2024 | Approved | HERBERT GIRON |