10210 N DEMPSEY AVE 91343

Certificate Information: 10210 N DEMPSEY AVE 91343

Application / Permit
22016-10000-35797
Plan Check / Job No.
B22LA23915
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) DETACHED GARAGE TO BE CONVERTED TO (N) DETACHED ADU PER ORDINANCE
Permit Issued
Issued on 4/7/2023
Issuing Office
Valley
Current Status
Issued on 4/7/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/28/2022 APPLICANT
Assigned to Plan Check Engineer 12/2/2022 FERNANDO FLORES
Corrections Issued 12/3/2022 FERNANDO FLORES
Building Plans Picked Up 12/7/2022 APPLICANT
Plan Check Approved 3/20/2023 FERNANDO FLORES
Issued 4/7/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/8/2022 FERNANDO GIL
Sewer availability Cleared 12/8/2022 FERNANDO GIL
Grading Pre-Inspection Cleared 12/13/2022 KIRK LINKLATER
Construction near power lines Cleared 3/5/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/20/2023 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/12/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 7/24/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 7/25/2023 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/16/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 10/16/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 10/16/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/16/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 11/28/2023 Approved JAVIER RAMOS JR
Insulation 11/28/2023 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 11/28/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 12/6/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Corrections Issued JAVIER RAMOS JR
Green Building Rough 12/6/2023 Approved JAVIER RAMOS JR
Insulation 12/6/2023 Approved JAVIER RAMOS JR
Drywall Nailing 12/18/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Approved JAVIER RAMOS JR
Shower Pan 12/18/2023 Approved JAVIER RAMOS JR
Sewer 4/17/2024 Approved JAVIER RAMOS JR
Underground Mechanical 4/17/2024 Corrections Issued JAVIER RAMOS JR
Final 8/15/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/15/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/15/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 8/29/2024 Approved JAVIER RAMOS JR
Final 8/29/2024 Corrections Issued JAVIER RAMOS JR
Gas Test 8/29/2024 Approved JAVIER RAMOS JR
Green Building Final 8/29/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 8/29/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 8/29/2024 Approved JAVIER RAMOS JR
Final 2/6/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/6/2025 Approved JAVIER RAMOS JR