4733-4735 N LIBBIT AVE 91436

Certificate Information: 4733-4735 N LIBBIT AVE 91436

Application / Permit
22016-10000-35492
Plan Check / Job No.
B22LA23751
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GARAGE CONVERSION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2022 APPLICANT
Assigned to Plan Check Engineer 12/5/2022 MOHAMMAD ESMAILI
Corrections Issued 12/6/2022 MOHAMMAD ESMAILI
Plan Check Approved 3/23/2023 DANIEL ABRAMYAN
Plan Check Approved 4/5/2023 DANIEL ABRAMYAN
Issued 4/25/2023 APPLICANT
CofO in Progress 4/18/2025 MORRIS JACKSON
Permit Finaled 4/22/2025 JOHN JANSON
CofO Issued 4/22/2025 JOHN JANSON
Permit Finaled 4/22/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/14/2022 COLIN LOREDO
Miscellaneous Cleared 12/14/2022 COLIN LOREDO
Sewer availability Cleared 12/14/2022 COLIN LOREDO
ZA Case Cleared 12/14/2022 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 1/18/2023 COLIN LOREDO
Construction near power lines Cleared 3/5/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: NA87698       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/23/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 8/24/2023 Approved SEAN HAUPT
Wood Frame 11/8/2023 Corrections Issued VINCENT HANLEY
Drywall Nailing 11/30/2023 Approved JEFFREY HARTLINE
Insulation 11/30/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 11/30/2023 Approved JEFFREY HARTLINE
Special/Order Compliance 11/30/2023 Approved JEFFREY HARTLINE
Final 10/29/2024 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 10/29/2024 Approved THOMAS FINNILA
Final 1/15/2025 Corrections Issued MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved MORRIS JACKSON
Final 4/18/2025 OK to Issue CofO MORRIS JACKSON