959 N SEWARD ST 2nd floor 90038
Certificate Information: 959 N SEWARD ST 2nd floor 90038
- Application / Permit
- 22016-10000-35488
- Plan Check / Job No.
- B22LA23747
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- New interior renovation to second floor corridor and elevator lobby. New fire rated corridor walls and new finishes. New fire rated suite entry doors. New elevator lobby finishes.
- Permit Issued
- Issued on 3/22/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/2/2023
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 12/6/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 1/13/2023 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/22/2023 | MICHAEL LOPEZ |
| Issued | 3/22/2023 | APPLICANT |
| Permit Finaled | 11/1/2023 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 3/8/2023 | PEJMAN NOORI |
Contact Information
| Architect | Wilder,, Arthur J; Lic. No.: NA27915 | , |
| Contractor | Esplanade Builders Inc; Lic. No.: 831964-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/19/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 4/27/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 4/27/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 4/28/2023 | Partial Approval | VAHE KELEDJIAN |
| Drywall Nailing | 5/2/2023 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 6/21/2023 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 6/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 6/22/2023 | Approved | ALFREDO LOPEZ |
| Final | 10/12/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 10/12/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 11/1/2023 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 11/1/2023 | Approved | ALFREDO LOPEZ |