1500 N SAN PABLO ST 90033
Certificate Information: 1500 N SAN PABLO ST 90033
- Application / Permit
- 22016-10000-35470
- Plan Check / Job No.
- B22LA23741
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- EPLAN: TENANT IMPROVEMENT TO (E) OFFICE BUILDING AND REPLACE TRANSFORMER. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/14/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/19/2024
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 12/3/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 1/4/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 2/9/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/12/2023 | GURUNATH NESARAJAH |
| Issued | 3/14/2023 | APPLICANT |
| Permit Finaled | 12/19/2024 | RONALD JIMENEZ |
Permit Application Clearance Information
| ZA Case | Cleared | 1/3/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 1/3/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 1/3/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 1/3/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 1/3/2023 | DALIA MOKAYED |
| Fire Marshal Fire Life Safety | Cleared | 2/21/2023 | VIDAL GARCIA |
| Redevelopment Project Area | Cleared | 2/23/2023 | GRACIELA ACOSTA |
Contact Information
| Architect | Joseph, H. Macdonald; Lic. No.: C34131 | , |
| Contractor | Hamilton Healthcare Construction Inc; Lic. No.: 698100-B | 202 MERCURY CIRCLE POMONA, CA 91768 |
| Engineer | Elhassan,, Rami Mohamed; Lic. No.: S3930 | 23 TRAILWOOD IRVINE, CA 92620 |
| Engineer | Ocampo,, Manolito Granda; Lic. No.: E16367 | 247 S DATE ST WEST ANAHEIM, CA 92805 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/8/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 6/15/2023 | Partial Approval | JULIAN CAPUCETTI |
| Light Gage Steel Frame | 6/15/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 6/21/2023 | Approved | JULIAN CAPUCETTI |
| Light Gage Steel Frame | 6/21/2023 | Approved | JULIAN CAPUCETTI |
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 7/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 7/20/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 8/10/2023 | Approved | JULIAN CAPUCETTI |
| T-Bar Ceiling | 8/10/2023 | Approved | JULIAN CAPUCETTI |
| Final | 12/19/2024 | Permit Finaled | RONALD JIMENEZ |
| Green Building Final | 12/19/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 12/19/2024 | Approved | RONALD JIMENEZ |